It is impossible to pass ISC2 CAP exam without any help in the short term. Come to Ucertify soon and find the most advanced, correct and guaranteed ISC2 CAP practice questions. You will get a surprising result by our Renovate ISC2 CAP Certified Authorization Professional practice guides.
Free CAP Demo Online For ISC2 Certifitcation:
NEW QUESTION 1
Gary is the project manager for his project. He and the project team have completed the qualitative risk analysis process and are about to enter the quantitative risk analysis process when
Mary, the project sponsor, wants to know what quantitative risk analysis will review. Which of the following statements best defines what quantitative risk analysis will review?
Answer: D
NEW QUESTION 2
In which of the following phases does the SSAA maintenance take place?
Answer: D
NEW QUESTION 3
Certification and Accreditation (C&A or CnA) is a process for implementing information security. It is a systematic procedure for evaluating, describing, testing, and authorizing systems prior to or after a system is in operation. Which of the following statements are true about Certification and Accreditation?
Each correct answer represents a complete solution. Choose two.
Answer: AD
NEW QUESTION 4
You are the project manager of the GHY Project for your company. You have completed the risk response planning with your project team. You now need to update the WBS. Why would the project manager need to update the WBS after the risk response planning process? Choose the best answer.
Answer: D
NEW QUESTION 5
You are the project manager for GHY Project and are working to create a risk response for a negative risk. You and the project team have identified the risk that the project may not complete on time, as required by the management, due to the creation of the user guide for the software you're creating. You have elected to hire an external writer in order to satisfy the requirements and to alleviate the risk event. What type of risk response have you elected to use in this instance?
Answer: C
NEW QUESTION 6
You are the project manager of the GHY project for your organization. You are working with your project team to begin identifying risks for the project. As part of your preparation for identifying the risks within the project you will need eleven inputs for the process. Which one of the following is NOT an input to the risk identification process?
Answer: C
NEW QUESTION 7
You are the project manager of QSL project for your organization. You are working you??re your project team and several key stakeholders to create a diagram that shows how various elements of a system interrelate and the mechanism of causation within the system. What diagramming technique are you using as a part of the risk identification process?
Answer: B
NEW QUESTION 8
An organization monitors the hard disks of its employees' computers from time to time. Which policy does this pertain to?
Answer: D
NEW QUESTION 9
Which of the following acts promote a risk-based policy for cost effective security?
Each correct answer represents a part of the solution. Choose all that apply.
Answer: AD
NEW QUESTION 10
Which of the following refers to the ability to ensure that the data is not modified or tampered with?
Answer: C
NEW QUESTION 11
The Software Configuration Management (SCM) process defines the need to trace changes, and the ability to verify that the final delivered software has all of the planned enhancements that are supposed to be included in the release. What are the procedures that must be defined for each software project to ensure that a sound SCM process is implemented?
Each correct answer represents a complete solution. Choose all that apply.
Answer: ABDE
NEW QUESTION 12
John is the project manager of the NHQ Project for his company. His project has 75 stakeholders, some of which are external to the organization. John needs to make certain that he communicates about risk in the most appropriate method for the external stakeholders. Which project management plan will be the best guide for John to communicate to the external stakeholders?
Answer: A
NEW QUESTION 13
Which of the following techniques are used after a security breach and are intended to limit the extent of any damage caused by the incident?
Answer: D
NEW QUESTION 14
Mark works as a project manager for TechSoft Inc. Mark, the project team, and the key project stakeholders have completed a round of qualitative risk analysis. He needs to update the risk register with his findings so that he can communicate the risk results to the project stakeholders - including management. Mark will need to update all of the following information except for which one?
Answer: B
NEW QUESTION 15
What does OCTAVE stand for?
Answer: B
NEW QUESTION 16
Your project uses a piece of equipment that if the temperature of the machine goes above 450 degree Fahrenheit the machine will overheat and have to be shut down for 48 hours. Should this machine overheat even once it will delay the project's end date. You work with your project to create a response that should the temperature of the machine reach 430, the machine will be paused for at least an hour to cool it down. The temperature of 430 is called what?
Answer: C
NEW QUESTION 17
Which of the following processes is a structured approach to transitioning individuals, teams, and organizations from a current state to a desired future state?
Answer: B
NEW QUESTION 18
What are the responsibilities of a system owner?
Each correct answer represents a complete solution. Choose all that apply.
Answer: ABC
NEW QUESTION 19
A Web-based credit card company had collected financial and personal details of Mark before issuing him a credit card. The company has now provided Mark's financial and personal details to another company. Which of the following Internet laws has the credit card issuing company violated?
Answer: B
NEW QUESTION 20
......
P.S. Easily pass CAP Exam with 395 Q&As 2passeasy Dumps & pdf Version, Welcome to Download the Newest 2passeasy CAP Dumps: https://www.2passeasy.com/dumps/CAP/ (395 New Questions)