NEW QUESTION 1

Which tool or technique is used in Close Procurements?

  • A. Contract plan
  • B. Procurement plan
  • C. Closure process
  • D. Procurement audits

Answer: D

NEW QUESTION 2

Which type of dependency is established based on knowledge of best practices within a particular application area or some unusual aspect of the project in which a specific
sequence is desired, even though there may be other acceptable sequences?

  • A. External
  • B. Internal
  • C. Mandatory
  • D. Discretionary

Answer: D

NEW QUESTION 3

Which type of project management office (PMO) supplies templates, best practices, and training to project teams?

  • A. Supportive
  • B. Directive
  • C. Controlling
  • D. Instructive

Answer: A

NEW QUESTION 4

Which type of analysis is used as a general management technique within the Plan Procurements process?

  • A. Risk assessment analysis
  • B. Make or buy analysis
  • C. Contract value analysis
  • D. Cost impact analysis

Answer: B

NEW QUESTION 5

Which of the following processes audits the quality requirements and the results from quality control measures to ensure appropriate quality standards and operational definitions are used?

  • A. Perform Quality Control
  • B. Quality Metrics
  • C. Perform Quality Assurance
  • D. Plan Quality

Answer: C

NEW QUESTION 6

Technical capability, past performance, and intellectual property rights are examples of:

  • A. performance measurement criteria
  • B. source selection criteria
  • C. product acceptance criteria
  • D. phase exit criteria

Answer: B

NEW QUESTION 7

Which grid shows which resources are tied to work packages?

  • A. Work breakdown structure (WBS)
  • B. Responsibility assignment matrix (RAM)
  • C. Project assignment chart
  • D. Personnel assignment matrix

Answer: B

NEW QUESTION 8

The project manager notes that stakeholders are aware of the project and potential impacts and are actively engaged in ensuring that the project is a success. The engagement level of the stakeholders should be classified as:

  • A. Supportive
  • B. Leading
  • C. Neutral
  • D. Resistant

Answer: B

NEW QUESTION 9

Which type of contract gives both the seller and the buyer flexibility to deviate from performance with financial incentives?

  • A. Cost Plus Incentive Fee (CPIF)
  • B. Fixed Price Incentive Fee (FPIF)
  • C. Cost Pius Award Re (CPAF)
  • D. Time and Material (T&M)

Answer: B

NEW QUESTION 10

Which process involves subdividing project deliverables and project work into smaller, more manageable portions?

  • A. Develop Schedule
  • B. Create VVBS
  • C. Estimate Activity Resources
  • D. Define Scope

Answer: B

NEW QUESTION 11

The process for performing variance analysis may vary, depending on:

  • A. scenario building, technology forecasting, and forecast by analogy.
  • B. working relationships among various stakeholders and team members.
  • C. application area, the standard used, and the industry,
  • D. work to be completed nex

Answer: C

NEW QUESTION 12

A large portion of a projects budget is typically expended on the processes in which Process Group?

  • A. Executing
  • B. Planning
  • C. Monitoring and Controlling
  • D. Closing

Answer: B

NEW QUESTION 13

What is the name of a graphic display of project team members and their reporting relationships?

  • A. Role dependencies chart
  • B. Reporting flow diagram
  • C. Project organization chart
  • D. Project team structure diagram

Answer: C

NEW QUESTION 14

In Plan Risk Management, which of the management plans determines who will be available to share information on various risks and responses at different times and locations?

  • A. Schedule
  • B. Quality
  • C. Communications
  • D. Cost

Answer: C

NEW QUESTION 15

The zero duration of milestones in project planning occurs because milestones:

  • A. Are unpredictable and challenge the Plan Schedule Management process.
  • B. Occur at random times in the project plans.
  • C. Represent a moment in time such as a significant project point or event.
  • D. Represent both significant and insignificant points in the project and are difficult to anticipat

Answer: C

NEW QUESTION 16

The procurement process that documents agreements and related documentation for future reference is known as:

  • A. Plan Procurements.
  • B. Control Procurements.
  • C. Close Procurements.
  • D. Conduct Procurement

Answer: C

NEW QUESTION 17

Testing falls into which of the following categories of cost of quality?

  • A. Internal failure costs
  • B. Prevention costs
  • C. Appraisal costs
  • D. External failure costs

Answer: C

NEW QUESTION 18

Which of the following is a tool or technique of the Define Activities process?

  • A. Rolling wave planning
  • B. Precedence diagramming method (PDM)
  • C. Alternatives analysis
  • D. Parametric estimating

Answer: A

NEW QUESTION 19

The Project Management Process Group in which performance is observed and measured regularly from project initiation through completion is:

  • A. Executing.
  • B. Initiating,
  • C. Monitoring and Controlling.
  • D. Plannin

Answer: C

NEW QUESTION 20

Prioritizing risks for further analysis or action by assessing and combining their probability of occurrence and impact takes place in which process?

  • A. Monitor and Control Risks
  • B. Plan Risk Management
  • C. Perform Qualitative Risk Analysis
  • D. Perform Quantitative Risk Analysis

Answer: C

NEW QUESTION 21

Which input will be used when tasked with developing the human resource plan?

  • A. Project management plan
  • B. Activity resource requirements
  • C. Resource calendar
  • D. Project staff assignments

Answer: B

NEW QUESTION 22

An input to the Manage Project Team process is:

  • A. Work performance reports.
  • B. Change requests.
  • C. Activity resource requirements.
  • D. Enterprise environmental factor

Answer: A

NEW QUESTION 23

What are the Project Procurement Management processes?

  • A. Conduct Procurements, Control Procurements, Integrate Procurements, and Close Procurements
  • B. Estimate Procurements, Integrate Procurements, Control Procurements, and Validate Procurements
  • C. Plan Procurement Management, Conduct Procurements, Control Procurements, and Close Procurements
  • D. Plan Procurement Management, Perform Procurements, Control Procurements, and Validate Procurements

Answer: C

NEW QUESTION 24

Which of the following statements is true regarding project and product lifecycles?

  • A. A single product lifecycle may consist of multiple project lifecycles.
  • B. A product lifecycle is always shorter than the project lifecycle.
  • C. A single product lifecycle can only have one project lifecycle.
  • D. A single project lifecycle may consist of multiple product lifecycle

Answer: A

NEW QUESTION 25

Which enterprise environmental factors are considered during Estimate Costs?

  • A. Market conditions and published commercial information
  • B. Company structure and market conditions
  • C. Commercial information and company structure
  • D. Existing human resources and market conditions

Answer: A

NEW QUESTION 26
......

P.S. Easily pass CAPM Exam with 704 Q&As Certifytools Dumps & pdf Version, Welcome to Download the Newest Certifytools CAPM Dumps: https://www.certifytools.com/CAPM-exam.html (704 New Questions)