Our pass rate is high to 98.9% and the similarity percentage between our CAPM study guide and real exam is 90% based on our seven-year educating experience. Do you want achievements in the PMI CAPM exam in just one try? I am currently studying for the PMI CAPM exam. Latest PMI CAPM Test exam practice questions and answers, Try PMI CAPM Brain Dumps First.

PMI CAPM Free Dumps Questions Online, Read and Test Now.

NEW QUESTION 1

Which process is usually a rapid and cost-effective means of establishing priorities for Plan Risk Responses?

  • A. Identify Risks
  • B. Plan Risk Management
  • C. Perform Qualitative Risk Analysis
  • D. Perform Quantitative Risk Analysis

Answer: C

NEW QUESTION 2

Which quality management and control tool is useful in visualizing parent-to-child relationships in any decomposition hierarchy that uses a systematic set of rules that define a nesting relationship?

  • A. Interrelationship digraphs
  • B. Tree diagram
  • C. Affinity diagram
  • D. Network diagram

Answer: B

NEW QUESTION 3

When a permitting agency takes longer than planned to issue a permit, this can be described as a risk:

  • A. event.
  • B. response,
  • C. perception.
  • D. impac

Answer: A

NEW QUESTION 4

The number of potential communication channels for a project with 5 stakeholders is:

  • A. 10.
  • B. 12.
  • C. 20.
  • D. 24.

Answer: A

NEW QUESTION 5

Which technique is commonly used for the Perform Quantitative Risk Analysis process?

  • A. Brainstorming
  • B. Strategies for opportunities
  • C. Decision tree analysis
  • D. Risk data quality assessment

Answer: C

NEW QUESTION 6

A project manager is appointed full-time to a project and is given full-time administrative staff and full-time project team members. This situation describes which type of organizational structure?

  • A. Projectized
  • B. Weak matrix
  • C. Functional
  • D. Balanced matrix

Answer: A

NEW QUESTION 7

The process of identifying and documenting the specific actions to be performed to produce the project deliverables is known as:

  • A. Define Activities.
  • B. Sequence Activities.
  • C. Define Scope.
  • D. Control Schedule.

Answer: A

NEW QUESTION 8

While implementing an approved change, a critical defect was introduced. Removing the defect will delay the product delivery. What is the MOST appropriate approach to managing this situation?

  • A. Utilize the change control process.
  • B. Crash the schedule to fix the defect.
  • C. Leave the defect in and work around it.
  • D. Fast-track the remaining developmen

Answer: A

NEW QUESTION 9

Which conflict resolution technique searches for solutions that bring some degree of satisfaction to all parties in order to temporarily or partially resolve the conflict?

  • A. Force/direct
  • B. Withdraw/avoid
  • C. Compromise/reconcile
  • D. Collaborate/problem solve

Answer: C

NEW QUESTION 10

In which Knowledge Area is the project charter developed?

  • A. Project Cost Management
  • B. Project Scope Management
  • C. Project Time Management
  • D. Project Integration Management

Answer: D

NEW QUESTION 11

A complete set of concepts, terms, and activities that make up an area of specialization is known as:

  • A. a Knowledge Area
  • B. a Process Group
  • C. program management
  • D. portfolio management

Answer: A

NEW QUESTION 12

Which Process Group includes the Manage Stakeholder Engagement process?

  • A. Executing
  • B. Planning
  • C. Monitoring and Controlling
  • D. Initiating

Answer: A

NEW QUESTION 13

The process of identifying the stakeholders' information needs is completed during:

  • A. Plan Communications.
  • B. Manage Stakeholder Expectations.
  • C. Stakeholder Analysis.
  • D. Identify Stakeholder

Answer: A

NEW QUESTION 14

The scope management plan and scope baseline are contained in:

  • A. organizational process assets
  • B. a requirements traceability matrix
  • C. the project charter
  • D. the project management plan

Answer: D

NEW QUESTION 15

Project contracts generally fall into which of the following three broad categories?

  • A. Fixed-price, cost reimbursable, time and materials
  • B. Make-or-buy, margin analysis, fixed-price
  • C. Time and materials, fixed-price, margin analysis
  • D. Make-or-buy, lump-sum, cost-plus-incentive

Answer: A

NEW QUESTION 16

Retreating from an actual or potential conflict or postponing the issue to be better prepared or to be resolved by others describes which of the five general techniques for managing conflict?

  • A. Smooth/accommodate
  • B. Withdraw/avoid
  • C. Compromise/reconcile
  • D. Force/direct

Answer: B

NEW QUESTION 17

Which Process Group and Knowledge Area include the Sequence Activities process?

  • A. Executing Process Group and Project Time Management
  • B. Executing Process Group and Project Cost Management
  • C. Planning Process Group and Project Time Management
  • D. Planning Process Group and Project Cost Management

Answer: C

NEW QUESTION 18

An output of the Manage Stakeholder Engagement process is:

  • A. change requests
  • B. enterprise environmental factors
  • C. the stakeholder management plan
  • D. the change log

Answer: A

NEW QUESTION 19

Projects that share common outcomes, collective capability, knowledge, or skills are often grouped into a:

  • A. portfolio
  • B. program
  • C. selection
  • D. sub portfolio

Answer: B

NEW QUESTION 20

Organizational process assets, a lessons-learned database, and historical information are all inputs to which process?

  • A. Plan Cost Management
  • B. Plan Scope Management
  • C. Plan Stakeholder Management
  • D. Plan Schedule Management

Answer: C

NEW QUESTION 21

When sequencing activities, what does the common acronym FF stand for?

  • A. Fixed Fee
  • B. Free Float
  • C. Fixed Finish
  • D. Finish-to-Finish

Answer: D

NEW QUESTION 22

Which is the correct formula for calculating expected activity cost for three-point estimating?

  • A. Ce = (C0 + 6Cm + Cp)/4
  • B. Ce = (6C0 + Cm + Cp)/4
  • C. Ce = (C0 + 4Cm + Cp)/6
  • D. Ce = (C0 + C„, + 4Cp) / 6

Answer: C