NEW QUESTION 1

Which tool or technique is used to manage change requests and the resulting decisions?

  • A. Change control tools
  • B. Expert judgment
  • C. Delphi technique
  • D. Change log

Answer: A

NEW QUESTION 2

A project management office manages a number of aspects including the:

  • A. Project scope, schedule, cost, and quality of the products of the work packages.
  • B. Central coordination of communication management across projects.
  • C. Assignment of project resources to best meet project objectives.
  • D. Overall risk, overall opportunity, and interdependencies among projects at the enterprise leve

Answer: D

NEW QUESTION 3

Which of the following techniques is used during Control Scope?

  • A. Cost-benefit analysis
  • B. Variance analysis
  • C. Reserve analysis
  • D. Stakeholder analysis

Answer: B

NEW QUESTION 4

Which tool or technique allows a large number of ideas to be classified into groups for review and analysis?

  • A. Nominal group technique
  • B. Idea/mind mapping
  • C. Affinity diagram
  • D. Brainstorming

Answer: C

NEW QUESTION 5

At which point of the project is the uncertainty the highest and the risk of failing the greatest?

  • A. Final phase of the project
  • B. Start of the project
  • C. End of the project
  • D. Midpoint of the project

Answer: B

NEW QUESTION 6

Which type of contract is most commonly used by buying organizations because the price for goods is set at the outset and is not subject to change unless the scope of work changes?

  • A. Fixed Price with Economic Price Adjustments Contract (FP-EPA)
  • B. Cost-Reimbursable Contract (CR)
  • C. Firm-Fixed -Price Contract (FFP)
  • D. Fixed-Price-Incentive-Fee Contract (FPIF)

Answer: C

NEW QUESTION 7

Which estimating technique uses the actual costs of previous similar projects as a basis for estimating the costs of the current project?

  • A. Analogous
  • B. Parametric
  • C. Bottom-up
  • D. Top-down

Answer: A

NEW QUESTION 8

Which change request is an intentional activity that realigns the performance of the project work with the project management plan?

  • A. Update
  • B. Preventive action
  • C. Defect repair
  • D. Corrective action

Answer: D

NEW QUESTION 9

What type of project structure is a hierarchically organized depiction of the resources by type?

  • A. Organizational breakdown structure (OBS)
  • B. Resource breakdown structure (RBS)
  • C. Work breakdown structure (WBS)
  • D. Project breakdown structure (PBS)

Answer: B

NEW QUESTION 10

The degree, amount, or volume of risk that an organization or individual will withstand is called risk:

  • A. appetite
  • B. tolerance
  • C. threshold
  • D. management

Answer: B

NEW QUESTION 11

A risk that arises as a direct result of implementing a risk response is called a:

  • A. contingent risk
  • B. residual risk
  • C. potential risk
  • D. secondary risk

Answer: D

NEW QUESTION 12

A technique used to determine the cause and degree of difference between baseline and actual performance is:

  • A. Product analysis.
  • B. Variance analysis.
  • C. Document analysis,
  • D. Decompositio

Answer: B

NEW QUESTION 13

In which Process Group are lessons learned documented?

  • A. Planning
  • B. Closing
  • C. Executing
  • D. Initiating

Answer: B

NEW QUESTION 14

Which of the following is a statistical concept that calculates the average outcome when the future includes scenarios that may or may not happen?

  • A. Sensitivity analysis
  • B. Three-point estimate
  • C. Modeling and simulation
  • D. Expected monetary value analysis

Answer: D

NEW QUESTION 15

The process of identifying and documenting relationships among the project activities is known as:

  • A. Control Schedule.
  • B. Sequence Activities.
  • C. Define Activities.
  • D. Develop Schedul

Answer: B

NEW QUESTION 16

Testing falls into which of the following categories of cost of quality?

  • A. Internal failure costs
  • B. Prevention costs
  • C. Appraisal costs
  • D. External failure costs

Answer: C

NEW QUESTION 17

Which tool or technique is required in order to determine the project budget?

  • A. Cost of quality
  • B. Historical relationships
  • C. Project management software
  • D. Forecasting

Answer: B

NEW QUESTION 18

A measure of cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal and is expressed as the ratio of the cost needed for finishing the outstanding work to the remaining budget is known as the:

  • A. budget at completion (BAC)
  • B. earned value management (EVM)
  • C. to-complete performance index
  • D. cost performance index

Answer: C

NEW QUESTION 19

During project selection, which factor is most important?

  • A. Types of constraints
  • B. Internal business needs
  • C. Budget
  • D. Schedule

Answer: B

NEW QUESTION 20

Which item is a formal proposal to modify any document, deliverable, or baseline?

  • A. Change request
  • B. Requirements documentation
  • C. Scope baseline
  • D. Risk urgency assessment

Answer: A

NEW QUESTION 21

At which stage of team development do members begin to work together, adjust work habits, and trust each other?

  • A. Forming
  • B. Storming
  • C. Norming
  • D. Performing

Answer: C

NEW QUESTION 22

Which of the following events would result in a baseline update?

  • A. A project is behind schedule and the project manager wants the baseline to reflect estimated actual completion.
  • B. A customer has approved a change request broadening the project scope and increasing the budget.
  • C. One of the risks identified in the risk management plan occurs, resulting in a schedule delay.
  • D. One of the key project team resources has left the team and no replacement is available.

Answer: B

NEW QUESTION 23
......