Our pass rate is high to 98.9% and the similarity percentage between our CAPM study guide and real exam is 90% based on our seven-year educating experience. Do you want achievements in the PMI CAPM exam in just one try? I am currently studying for the PMI CAPM exam. Latest PMI CAPM Test exam practice questions and answers, Try PMI CAPM Brain Dumps First.
Free demo questions for PMI CAPM Exam Dumps Below:
NEW QUESTION 1
Which Define Activities output extends the description of the activity by identifying the multiple components associated with each activity?
Answer: C
NEW QUESTION 2
Which process involves subdividing project deliverables and project work into smaller, more manageable portions?
Answer: B
NEW QUESTION 3
Which of the Perform Quality Assurance tools and techniques may enhance the creation of the work breakdown structure (VVBS) to give structure to the decomposition of the scope?
Answer: B
NEW QUESTION 4
What does a CPI value greater than 1.0 indicate?
Answer: B
NEW QUESTION 5
During which process does a project manager review all prior information to ensure that all project work is completed and that the project has met its objectives?
Answer: C
NEW QUESTION 6
Organizational planning impacts projects by means of project prioritization based on risk, funding, and an organizations:
Answer: D
NEW QUESTION 7
Which of the following statements is true regarding project and product lifecycles?
Answer: A
NEW QUESTION 8
In the Plan Stakeholder Management process, expert judgment is used to:
Answer: D
NEW QUESTION 9
Which type of contract is a hybrid of both a cost-reimbursable and a fixed-price contract?
Answer: C
NEW QUESTION 10
What is the probability of occurrence if the risk rating is 0.56 and the impact if the risk does occur is very high (0.80)?
Answer: C
NEW QUESTION 11
Which stakeholder approves a project's result?
Answer: A
NEW QUESTION 12
What are the formal and informal policies, procedures, and guidelines that could impact how the project's scope is managed?
Answer: A
NEW QUESTION 13
An output of the Create WBS process is:
Answer: A
NEW QUESTION 14
Change requests, project management plan updates, project document updates, and organizational process assets updates are all outputs of which project management process?
Answer: B
NEW QUESTION 15
Which of the following is a tool and technique for Estimate Activity Durations?
Answer: A
NEW QUESTION 16
In Plan Risk Management, which of the management plans determines who will be available to share information on various risks and responses at different times and locations?
Answer: C
NEW QUESTION 17
The integrative nature of project management requires which Process Group to interact with the other Process Groups?
Answer: C
NEW QUESTION 18
Which of the following correctly explains the term "progressive elaboration'?
Answer: D
NEW QUESTION 19
An input to the Perform Integrated Change Control process is:
Answer: D
NEW QUESTION 20
Which is one of the major outputs of Sequence Activities?
Answer: C
NEW QUESTION 21
Which activity is an input to the Conduct Procurements process?
Answer: A
NEW QUESTION 22
What is the definition of Direct and Manage Project Execution?
Answer: B
NEW QUESTION 23
......
100% Valid and Newest Version CAPM Questions & Answers shared by Surepassexam, Get Full Dumps HERE: https://www.surepassexam.com/CAPM-exam-dumps.html (New 704 Q&As)