CAPM Exam - Certified Associate in Project Management (PMI-100)

certleader.com

Our pass rate is high to 98.9% and the similarity percentage between our CAPM study guide and real exam is 90% based on our seven-year educating experience. Do you want achievements in the PMI CAPM exam in just one try? I am currently studying for the PMI CAPM exam. Latest PMI CAPM Test exam practice questions and answers, Try PMI CAPM Brain Dumps First.

Free demo questions for PMI CAPM Exam Dumps Below:

NEW QUESTION 1

Which Define Activities output extends the description of the activity by identifying the multiple components associated with each activity?

  • A. Project document updates
  • B. Activity list
  • C. Activity attributes
  • D. Project calendars

Answer: C

NEW QUESTION 2

Which process involves subdividing project deliverables and project work into smaller, more manageable portions?

  • A. Develop Schedule
  • B. Create VVBS
  • C. Estimate Activity Resources
  • D. Define Scope

Answer: B

NEW QUESTION 3

Which of the Perform Quality Assurance tools and techniques may enhance the creation of the work breakdown structure (VVBS) to give structure to the decomposition of the scope?

  • A. Activity network diagrams
  • B. Affinity diagrams
  • C. Matrix diagrams
  • D. Interrelationship digraphs

Answer: B

NEW QUESTION 4

What does a CPI value greater than 1.0 indicate?

  • A. Cost right at the estimated value
  • B. Cost under the estimated value
  • C. Cost right at the actual value
  • D. Cost over the estimated value

Answer: B

NEW QUESTION 5

During which process does a project manager review all prior information to ensure that all project work is completed and that the project has met its objectives?

  • A. Monitor and Control Project Work
  • B. Perform Quality Assurance
  • C. Close Project or Phase
  • D. Control Scope

Answer: C

NEW QUESTION 6

Organizational planning impacts projects by means of project prioritization based on risk, funding, and an organizations:

  • A. Budget plan
  • B. Resource plan
  • C. Scope plan
  • D. Strategic plan

Answer: D

NEW QUESTION 7

Which of the following statements is true regarding project and product lifecycles?

  • A. A single product lifecycle may consist of multiple project lifecycles.
  • B. A product lifecycle is always shorter than the project lifecycle.
  • C. A single product lifecycle can only have one project lifecycle.
  • D. A single project lifecycle may consist of multiple product lifecycle

Answer: A

NEW QUESTION 8

In the Plan Stakeholder Management process, expert judgment is used to:

  • A. Provide information needed to plan appropriate ways to engage project stakeholders.
  • B. Ensure comprehensive identification and listing of new stakeholders.
  • C. Analyze the information needed to develop the project scope statement.
  • D. Decide the level of engagement of the stakeholders at each required stag

Answer: D

NEW QUESTION 9

Which type of contract is a hybrid of both a cost-reimbursable and a fixed-price contract?

  • A. Cost Plus Award Fee Contract (CPAF)
  • B. Firm-Fixed -Price Contract (FFP)
  • C. Time and Material Contract (T&M)
  • D. Cost Plus Incentive Fee Contract (CPIF)

Answer: C

NEW QUESTION 10

What is the probability of occurrence if the risk rating is 0.56 and the impact if the risk does occur is very high (0.80)?

  • A. 0.45
  • B. 0.56
  • C. 0.70
  • D. 1.36

Answer: C

NEW QUESTION 11

Which stakeholder approves a project's result?

  • A. Customer
  • B. Sponsor
  • C. Seller
  • D. Functional manager

Answer: A

NEW QUESTION 12

What are the formal and informal policies, procedures, and guidelines that could impact how the project's scope is managed?

  • A. Organizational process assets
  • B. Enterprise environmental factors
  • C. Project management processes
  • D. Project scope management plan

Answer: A

NEW QUESTION 13

An output of the Create WBS process is:

  • A. Scope baseline.
  • B. Project scope statement.
  • C. Organizational process assets.
  • D. Requirements traceability matri

Answer: A

NEW QUESTION 14

Change requests, project management plan updates, project document updates, and organizational process assets updates are all outputs of which project management process?

  • A. Plan Risk Responses
  • B. Manage Stakeholder Expectations
  • C. Define Scope
  • D. Report Performance

Answer: B

NEW QUESTION 15

Which of the following is a tool and technique for Estimate Activity Durations?

  • A. Parametric estimating
  • B. Monte Carlo analysis
  • C. Alternatives analysis
  • D. Bottom-up estimating

Answer: A

NEW QUESTION 16

In Plan Risk Management, which of the management plans determines who will be available to share information on various risks and responses at different times and locations?

  • A. Schedule
  • B. Quality
  • C. Communications
  • D. Cost

Answer: C

NEW QUESTION 17

The integrative nature of project management requires which Process Group to interact with the other Process Groups?

  • A. Planning
  • B. Executing
  • C. Monitoring and Controlling
  • D. Project Management

Answer: C

NEW QUESTION 18

Which of the following correctly explains the term "progressive elaboration'?

  • A. Changing project specifications continuously
  • B. Elaborate tracking of the project progress
  • C. Elaborate tracking of the project specifications with a change control system
  • D. Project specifications becoming more explicit and detailed as the project progresses

Answer: D

NEW QUESTION 19

An input to the Perform Integrated Change Control process is:

  • A. expert judgment
  • B. seller proposals
  • C. the project charter
  • D. the project management plan

Answer: D

NEW QUESTION 20

Which is one of the major outputs of Sequence Activities?

  • A. Responsibility assignment matrix (RAM)
  • B. Work breakdown structure (WBS) update
  • C. Project schedule network diagram
  • D. Mandatory dependencies list

Answer: C

NEW QUESTION 21

Which activity is an input to the Conduct Procurements process?

  • A. Organizational process assets
  • B. Resource availability
  • C. Perform Integrated Change Control
  • D. Team performance assessment

Answer: A

NEW QUESTION 22

What is the definition of Direct and Manage Project Execution?

  • A. Integrating all planned activities
  • B. Performing the activities included in the plan
  • C. Developing and maintaining the plan
  • D. Execution of deliverables

Answer: B

NEW QUESTION 23
......

100% Valid and Newest Version CAPM Questions & Answers shared by Surepassexam, Get Full Dumps HERE: https://www.surepassexam.com/CAPM-exam-dumps.html (New 704 Q&As)