Your success in The-Open-Group OG0-092 is our sole target and we develop all our OG0-092 braindumps in a way that facilitates the attainment of this target. Not only is our OG0-092 study material the best you can find, it is also the most detailed and the most updated. OG0-092 Practice Exams for The-Open-Group {category} OG0-092 are written to the highest standards of technical accuracy.

NEW QUESTION 1
FreshFruit Int. is an online American grocer. The Executive Board decided to implement a new strategy to expand the business to other markets.
The CIO is sponsoring an enterprise activity to support the expanded operations.
A new solution is rolled-out to replace the legacy online sales platform. A compliance review was performed to assess the solution implementation.
The result of the review highlighted a complaint from the development team stating that the new system is difficult to integrate with the existing warehouse automation systems. The Chief Architect is concerned that the complaint is not related to a real problem of the solution but is based on personal preferences of the development teams. Another interview with the project team is scheduled.
Refer to the scenario above You are the Lead Architect and an architect from your team leads the review team. You have to answer how, based on TOGAF 9, you should enable the review team to conduct the reviews successfully.
Choose one of the following answers

  • A. Meeting with the project architect you clarify the purpose of the revie
  • B. You ask to perform an objective and fair review using the checklists to frame the review and clarify that you want them to identify the issues behind the implementation team complaints.
  • C. You organize a meeting with the review team and state the importance to identify any non-compliancy that may have come from the implemented solution.
  • D. You organize a meeting with the review team and stress the importance of a high degree of compliance without any exceptio
  • E. The review should cover every aspect of the implementation and should criticize the implementation techniques.
  • F. You verify that criteria for the program and the business objectives are mapped in the checklists that the project team prepared for the interview
  • G. You confirm the checklist content to the project architect and stress the need to be objective and fair during the review process.

Answer: D

NEW QUESTION 2
TP Banking is a strong financial institute with a well-known acquisition history with an internal IT department managing over 100 projects related to infrastructure and services.
The CIO has decided to create an Enterprise Architecture based on TOGAF 9 as reaction to the difficult market conditions. An Architecture Vision and a set of domain architectures were approved. The CIO is asking you (the Lead Architect) to define an Implementation and Migration Plan that realizes the vision already agreed with the stakeholders involved.
Refer to the scenario above
You are leading a group of domain architects and you are working with the corporate PMO, the business strategy team and service operations. You are meeting the stakeholders to clarify how you want to proceed with the Implementation and Migration Plan.
Choose one of the following answers

  • A. You propose to start collecting the existing deliverables describing the different domains in order to enable the Enterprise Architecture tram to integrate them with the support of the operation managemen
  • B. Every domain architect will then evaluate the impact on the projects already planned for the domai
  • C. The single revised plans will be integrated together and consolidated into a strategic implementation and migration strategy defining an IT roadmap.
  • D. You communicate the need for urgenc
  • E. The projects already planned will be cancelled and the implementation of the new architecture vision will be set as first priorit
  • F. A set of new projects will be defined to implement the new strateg
  • G. You will use the requirements from Phases B through D and define new projects for each one of the requirement
  • H. The use of defined interoperability architecture guidelines will then enable the project teams to work together and define a set of new point-to-point interfaces.
  • I. You describe the concept of Transition Architectures and clarify that the business value can be achieved by all the projects delivering their increments in a coordinated approac
  • J. Capability gaps and project dependencies are analyzed for each domain this will then enable the projects to be organized in work package
  • K. You will then agree on the roadmap for the implementation and migration strategy meeting with all the key stakeholders.
  • L. You communicate the CIO's will to transform the corporation and then that he's seeking help from the domain architects to do tha
  • M. The requirements are managed in order to enable every Architect to participate to the planning that will result in a detailed list of work activities with impact on the IT portfolio of project
  • N. A five year Target Architecture will then be defined and a report will keep track of dependencies and factors assessment.

Answer: C

NEW QUESTION 3
Scenario: Zephyr Enterprises
Please read this scenario prior to answering the question
Zephyr Enterprises specializes in the development of wind turbine blades for use in large- scale commercial wind energy production systems. Zephyr has manufacturing facilities located in Palm Springs, California, Omaha, Nebraska, and Winnipeg, Ontario. Each of these plants supplies a different manufacturer that builds and sells complete systems. The turbine blades are custom engineered to meet each manufacturers design specifications.
Until recently, most turbine blades were fabricated manually using molded fiber-reinforced plastics. However, recent improvements in composite materials, coupled with enhanced automated methods for precision application of materials during the molding process, have led to significant reduction in weight, increase in strength, and greatly improved blade longevity. Zephyr has pioneered the development of a proprietary automated process for continuous extrusion of the turbine blades. Patents have been filed to protect the process, but certain trade secrets must be closely guarded.
Zephyr has a mature Enterprise Architecture organization that is supported by a cross- functional Architecture Review Board. The Chief Information Officer and the Chief Operating Officer co-sponsor the Enterprise Architecture program.
Zephyr has used TOGAF and its Architecture Development Method (ADM) to develop its automated manufacturing processes and systems that are used to design, manufacture, and test the blade assemblies. They have recently updated to TOGAF 9 and have adapted the Zephyr Enterprise Architecture to closely follow the TOGAF 9 framework. All of Zephyrs IT architects have been trained and certified on TOGAF 9.Recently, an architecture project was completed that defined a standard approach for controlling the Automated Test System that is used at each plant to perform final quality assurance tests on each completed blade assembly. The Manufacturing Architecture Board approved the plan for immediate implementation at each plant.
An Architecture Contract was developed that detailed the work needed to implement and deploy the new Automated Test System controller. The Chief Engineer, sponsor of the activity, has expressed concern that a uniform process be employed at each site to ensure consistency.
Refer to the Zephyr Enterprises Scenario:
You have been assigned by the Lead Architect for the Automated Test System controller project to conduct Compliance Assessments at each manufacturing plant.
During the course of the assessment at the Omaha plant, you discover that the Distributed Data Acquisition System they have purchased uses a proprietary Remote Procedure Call (RPC) that utilizes kernel mode threads instead of the user mode threads that are specified in the Architecture Definition Document. In all other respects, the system meets the requirements stated in the Architecture Definition Document and seems to perform correctly.
You have been asked to describe the compliance of this system for the final report. Based on TOGAF 9, which of the following is the best answer?

  • A. You observe that all of the features in the Architecture Definition Document have been implemented in accordance with the specification, except for the RPC mechanis
  • B. Your recommendation is that the system be described as conformant.
  • C. You observe that the system has many features in common with the Architecture Definition Document, and those features have been implemented in accordance with the specificatio
  • D. However, you note that the RPC mechanism has been implemented using features that are not covered by the specificatio
  • E. Your recommendation is that the system be described as consistent.
  • F. You observe that the implementation of the RPC mechanism has no features in common with the Architecture Definition Document, therefore the question of its conformance should not be considere
  • G. Your recommendation is that the system be described as consistent.
  • H. You observe that the system meets most of the requirements stated in the Architecture Definition Document and appears to work correctl
  • I. However, you note that the RPC mechanism has not been implemented according to the specificatio
  • J. Your recommendation is that the system be described as non-conformant.

Answer: D

NEW QUESTION 4
Scenario:
Please read this scenario prior to answering the Question
You have been appointed as a consultant to the Lead Enterprise Architect of an international agricultural company that exports bulbs, flowers and seeds worldwide. The company has its headquarters in the Netherlands, and has sales and distribution centers in over 30 countries worldwide. Several of these centers include administrative, manufacturing, and research facilities.
To achieve full integration of their research capabilities with their development centers located in various climate zones, the company wants to develop strong self-directed teams in each location. It also wants to define new business models that are profitable while reducing their impact on the environment. The management team is deeply committed to ensuring that the company is a world leader in socially responsible seed development with a business strategy that focuses on profitability through environmentally friendly operating processes.
The international operations of the company are subject to legal and regulatory requirements for each country where they operate. The production of genetically modified seeds has governmental controls that are strictly enforced and compliance is critical. Recently a competitor was heavily fined for violating the regulations in a country where it was developing pest-resistant seeds.
The Governing Board is concerned about the risks posed in this complex global environment, and as a result has approved the expenditure of resources to establish an Enterprise Architecture program. They have requested to be informed about the status of projects that could impact regulatory compliance. They also want to enable the corporate legal staff and auditors to analyze proposed architectures to ensure that they are within the legal guidelines for a given location. In addition, the research organization should be able to see that the architecture is appropriate for its needs.
TOGAF 9 has been mandated as the framework for the development and evolution of the Enterprise Architecture practice. The Preliminary Phase has been completed to establish the enterprise architecture capability for this project.
Refer to the Scenario
You have been asked to recommend an approach that would enable the development of an architecture that addresses the needs of the Governing Board, legal staff, auditors and the research organization.
Based on TOGAF 9, which of the following is the best answer?

  • A. You recommend that each project architecture activity is developed using a consistent modeling approach that is uniform across all architecture project
  • B. Each architecture should be defined based on this fixed set of models so that all concerned parties can examine the models to ensure that their issues and concerns have been addressed.
  • C. You recommend that a special report be created for those groups that have sufficient power and level of interes
  • D. This report should summarize the key features of the architecture with respect to the particular locatio
  • E. Each of these reports should reflect the stakeholders1 requirements.
  • F. You recommend that a set of models be created for each project architecture that can be used to ensure that the system will be compliant with the local regulation
  • G. Stakeholders should then view the models to verify that their concerns have been properly addressed.
  • H. You recommend that a stakeholder map be develope
  • I. This will allow the architects to define groups of stakeholders that share common concern
  • J. A set of views should be defined to address the concerns for each group of stakeholder
  • K. Architecture models should then be created for each view to address the stakeholders' concerns.

Answer: D

NEW QUESTION 5
Scenario:
Please read this scenario prior to answering the question
You are serving as the Lead Enterprise Architect at a major supplier in the automotive industry. The company is headquartered in Cleveland, Ohio with manufacturing plants across the United States, Brazil, Germany, Japan and South Korea. Each of these plants has been operating its own planning and production scheduling systems, as well as custom developed applications that drive the automated production equipment at each plant.
The company is implementing lean manufacturing principles to minimize waste and improve the efficiency of all of its production operations. During a recent exercise held for internal quality improvement, it was determined that a significant reduction in process waste could be achieved by replacing the current planning and scheduling systems with a common Enterprise Resource Planning (ERP) system located in the Cleveland data center. This central system would provide support to each of the plants replacing the functionality in the existing systems. It would also eliminate the need for full data centers at each of the
plant facilities. A reduced number of IT staff could support the remaining applications. In some cases, a third-party contractor could provide those staff.
The Enterprise Architecture department has been operating for several years and has mature, well-developed architecture governance and development processes that are strongly based on TOGAF 9.
At a recent meeting, the Architecture Board approved a Request for Architecture Work sponsored by the Chief Engineer of Global Manufacturing Operations. The request covered the initial architectural investigations and the development of a comprehensive architecture to plan the transformation.
The Common ERP Deployment architecture project team has now been formed, and the project team has been asked to develop an Architecture Vision that will achieve the desired outcomes and benefits. Some of the plant managers have expressed concern about the security and reliability of diving their planning and production scheduling from a remote centralized system. The Chief Engineer wants to know how these concerns can be addressed.
Refer to the Scenario
[Note: You should assume that the company has adopted the example set of principles that are listed and defined in TOGAF 9, Section 23.6.]
One of the earliest initiatives in the Enterprise Architecture program was the definition of a set of architecture principles. These now need to be updated to address the concerns raised.
You have been asked to select a set of principles most appropriate for guiding the team to define a robust solution.
Based on TOGAF 9, which of the following is the best answer?

  • A. Common-use Applications, Control Technical Diversity, Ease of Use, Interoperability, Data is Shared, Data is Accessible, Data Security
  • B. Business Continuity, Common-use Applications, Maximize Benefit to the Enterprise, Data is Shared, Data is Accessible, Data Security
  • C. Technology Independence, Data Trustee, Information Management is Everybody's Business, IT Responsibility, Responsive Change Management
  • D. Service-orientation, Responsive Change Management, Business Continuity, Data is Accessible, Data Security

Answer: B

NEW QUESTION 6
Scenario: AGEX Inc.
Please read this scenario prior to answering the question
AGEX is a large, global commodities trading company which has been growing rapidly through a series of acquisitions.
Each new business is performing well in its markets. However, the lack of integration between headquarters and the business units has increasingly caused problems in the handling of customer and financial information. The inability to share information across businesses has resulted in lost opportunities to "leverage the synergies" that had been intended when the businesses were acquired. At present, each business unit maintains its own applications. Despite an earlier initiative to install a common application to manage customer, products, supplier, and inventory information, each business unit has different ways of defining each of these core elements and has customized the common application to the point where the ability to exchange information is difficult, costly, and error-prone.
As a result, AGEX has begun implementing a single Enterprise Resource Planning (ERP) system to consolidate information from several applications that exist across the lines of
business. The Corporate Board is concerned that the new ERP system must be able to manage and safeguard customer information in a manner that meets or exceeds the legal requirements of the countries in which the company operates. This will be an increasingly important capability as the company expands its online services offered to clients and trading partners.
The CIO has formed an Enterprise Architecture department, and one of the primary goals in its charter is to coordinate efforts between the ERP implementation team and the business unit personnel who will be involved in the migration process. The CIO has also formed a cross-functional Architecture Review Board to oversee and govern the architecture.
After reviewing the available alternatives, and based on recommendations from the ERP vendor, AGEX has selected TOGAF 9 as the basis for its Enterprise Architecture program.
The CIO has endorsed this choice with the full support of top management. Refer to the AGEX Inc. Scenario
You are serving as the Chief Architect.
As part of the process for establishing the Enterprise Architecture department, you have decided to create a set of principles to guide the activities.
You have been asked to recommend the best approach for this work. Based on TOGAF 9, which of the following is the best answer?

  • A. You define a set of principles that support the preferred best practices embodied in the Enterprise Architecture department charte
  • B. You publish the principles on the corporate intranet to ensure widespread acceptance and compliance.You then schedule regular periodic Compliance Assessments with individual business units to check that they have made satisfactory progress toward meeting the objectives and conditions embodied in the principles.
  • C. You gather information from credible industry sources in the commodities busines
  • D. Based on that, you assess current trends and apply that to defining a set of principles that embody best practices.You select architecture principles that do not conflict with each other and that should be stabl
  • E. You ensure that all the principles are realistic and avoid including principles that are obvious.
  • F. You examine the mission statements for AGEX and each of its businesses, togetherwith the corporate value statement
  • G. Based on that, you define a set of principles and review with the CIO.When developing the principles you ensure that they actively promote the alignment of IT with the business strategies and initiatives of AGE
  • H. You then seek the endorsement of the CIO and senior management.
  • I. You examine the mission statements for AGEX and each of its businesses, together with the corporate value statement
  • J. Based on that, you work with the Architecture Review Board to define the principles.When developing the principles you ensure that they actively promote the alignment of IT with the AGEX business strategie
  • K. You then run a series of reviews with all the relevant stakeholders, including senior management, ensuring their support.

Answer: D

NEW QUESTION 7
Scenario:
Please read this scenario prior to answering the question
You are the Lead Enterprise Architect in a company that specializes in the development of wind turbine blades for use in large-scale commercial wind energy production systems. The company has manufacturing facilities located in Illinois, Nebraska, and Manitoba. Each of these plants supplies a different manufacturer that builds and sells complete systems. The turbine blades are custom engineered to meet each manufacturer's design specifications.
Until recently, most turbine blades were fabricated manually using molded fiber-reinforced plastics. However, recent improvements in composite materials, coupled with enhanced automated methods for precision application of materials during the molding process, have led to significant reduction in weight, increase in strength, and improved blade longevity. The company has pioneered the development of a proprietary automated process for continuous extrusion of the turbine blades. Patents have been filed to protect the process, but certain trade secrets must be closely guarded.
The company has a mature Enterprise Architecture organization that is supported by a cross-functional Architecture Board. The Chief Information Officer and the Chief Operating Officer co-sponsor the Enterprise Architecture program.
TOGAF 9 and its Architecture Development Method (ADM) are used to develop the automated manufacturing processes and systems that are used to design, manufacture, and test the blade assemblies.
Recently, a pilot architecture project was completed at a single location that defined a standard approach for controlling the Automated Test System that is used at each plant to perform final quality assurance tests on each completed blade assembly. The Architecture
Board approved the plan for immediate implementation at each plant.
Architecture Contracts have been developed that detail the work needed to implement and deploy the new Automated Test System controller for each location. The Chief Engineer, sponsor of the activity, has expressed concern that a uniform process be employed at each location to ensure consistency.
Refer to the Scenario
You have been asked to recommend the best approach to address the Chief Engineer's concern.
Based on TOGAF 9, which of the following is the best answer?

  • A. You review the applicable Architecture Contract for each location, ensuring that it addresses the project objectives, effectiveness metrics, acceptance criteria, and risk managemen
  • B. In cases where the contract is issued to an external party, you ensure that it is a legally enforceable contract.You schedule compliance reviews at key points in the implementation process to ensure that the work is proceeding in accordance with the Architecture Definitio
  • C. You ensure that the Architecture Board reviews all deviations from the Architecture Contract, and considers whether or not to grant a dispensation to allow the implementation organization to customize the process to meet their local needs.
  • D. You create an Architecture Contract to manage and govern the implementation and migration process at each locatio
  • E. For internal development projects, you issue a memorandum of understanding between the Architecture Board and the implementation organizatio
  • F. For contracts issued to an external party, you ensure that it is a fully enforceable legal contract.You ensure that the Architecture Board reviews all deviations from the Architecture Contract, and considers whether or not to grant a dispensation to allow the implementation organization to customize the process to meet their local needs.
  • G. You create an Architecture Contract to manage and govern the implementation and migration proces
  • H. If the contract is issued to an external party, you ensure that it is a fully enforceable legal contrac
  • I. For internal development projects, you decide it is adequate to utilize a memorandum of understanding between the Architecture Board and the implementation organization.You recommend that if a deviation from the Architecture Contract is detected, the Architecture Board grant a dispensation to allow the implementation organization the ability to customize the process to meet their local needs.
  • J. You use the issued Architecture Contracts to manage the architecture governance processes for the project across the location
  • K. You deploy monitoring tools to assess the performance of the completed blade assembly at each location and develop change requirements if necessary.You recommend that if a deviation from the contract is detected, the Architecture Board should modify the Architecture Contract to allow the implementation organization the abilityto customize the process to meet their local need
  • L. As a result, you then issue a new Request for Architecture Work to implement the modified Architecture Definition.

Answer: A

NEW QUESTION 8
Scenario: Vittronics Ltd.
Please read this scenario prior to answering the question
Vittronics Ltd. is a leading medical device manufacturer in the highly competitive market for Migraine Headache Pain Management (MHPM) devices. These tiny wireless devices are implanted in the brain and can deliver a precise electric shock when the wearable Pain Control Unit (PCU) detects an increase in stress induced by the onset of a migraine headache.
This technology will be a breakthrough in the treatment of this condition, and several competitors are striving to be the first to introduce a product into the market. However, all of them must demonstrate the effectiveness and safety of their products in a set of clinical trials that will satisfy the regulatory requirements of the countries in the target markets.
The Enterprise Architecture group at Vittronics has been engaged in an architecture development project to create a Secure Private Immersive Collaborative Environment (SPICE) that will allow researchers at its product development laboratories worldwide to share information about their independent clinical trials.
The Vittronics Enterprise Architecture group is a mature organization that has been utilizing TOGAF for several years. They have recently upgraded to TOGAF 9. The Vittronics Architecture Development Method (VADM) is strictly based on the TOGAF 9 Architecture Development Method (ADM) with extensions required to support current good manufacturing practices and good laboratory practices in their target markets.
The SPICE project team has now completed the Business, Information Systems, and Technology Architecture phases and has produced a complete set of deliverables for each phase. Due to the highly sensitive nature of the information that is managed in SPICE, special care was taken to ensure that each architecture domain included an examination of the security and privacy issues that are relevant for each domain. A corresponding SPICE Security Architecture has been defined.
The Executive Vice President for Clinical Research is the sponsor of the Enterprise Architecture activity.
Refer to the Vittronics Ltd Scenario:
You are serving as the Lead Architect for the SPICE project team.
As required by TOGAF, the SPICE project team res completed a Business Transformation Readiness Assessment in Phase A (Architecture Vision). In that assessment, it was determined that there are risks associated with the adoption of the Immersive Collaborative Environment. Despite a clear expression of the vision and the business need for utilizing SPICE to accelerate the clinical trials, the researchers have been resisting the change because of concerns about safeguarding individually identifiable information about the subjects who were participating in the trials.
You have been asked to recommend how this situation be managed in the implementation planning phases.
Based on TOGAF 9, which of the following is the best answer?

  • A. You decide that in Phase E, the team creates an overall solutions strategy that can guide the Target Architecture implementation and structure the Transition Architecture
  • B. You check that there is consensus before proceeding.
  • C. You decide to return to Phase A, where the team should brainstorm a technical solution that mitigates the residual risks presented by the privacy issu
  • D. Then, during Phase D, you will direct the team to develop an Architecture Building Block to manage the security risk
  • E. After that, the team should select Solution Building Blocks that mitigate all of the identified risks and revise the Requirements Impact Statement to reflect the changes to the high-level solutions strategy and migration plan.
  • F. You decide that in Phase E, the team review the Business Transformation Readiness Assessment and identify, classify, and mitigate the risks associated with the identified readiness factor
  • G. If the risks can be satisfactorily mitigated, then you would continue to define a high-level solutions strategy that includes the Transition Architectures needed to make the change culturally and technically feasible.
  • H. You decide that in Phase E, the team determines an approach to implementing an overall strategic direction that will address and mitigate the risks identified.

Answer: B

NEW QUESTION 9
Magic Wand Corporation manufactures a range of equipment used by magician worldwide. The global popularity of a series of children’s books describing the formative years of a budding wizard and his various escapades at wizard school has driven unprecedented sales growth in the magical equipment market.
The current IT systems at Magic Wand are struggling to cope with the high volumes in this growth market. The CIO wants to persuade the board of Magic Wand Corporation to make a greater investment in the IT systems to cope with the new higher transaction volumes. On of the key components the CIOs wants to include when he approaches the board is a description of the current problems and how they may be addressed from an architectural point of view.
As the High Architect of Magic Wand Corporation, the CIO has delegated the task of
creating a vision for the future Architecture to you.
Which of the following answers best describes how TOGAF recommends delivering an Architecture Vision for the CIO?

  • A. Firstly, I ensure there is a Request for Architecture Work from the CI
  • B. Then I ensure that there is recognition for the architecture vision project by following any project management and programmed management frameworks used within the organizatio
  • C. I would identify the key stakeholders and engage with them to understand and document their concerns and high-level requirement
  • D. This would result in a stakeholder map used to support other deliverables such as the Architecture Vision, a Communications plan and a Statement of Architecture Wor
  • E. I would then identify the business goals and strategic drivers of the organization and define any enterprise or project specific constraints such as time and resource
  • F. I would then define the business capabilities of the organization needed to fulfill those business goals and drivers and their readiness for chang
  • G. Once complete, I would define the scope, confirm the architecture and business principles and develop the Architecture Visio
  • H. Following this, I would define the business case for the architecture project, assess the business risks and produce a risk mitigation pla
  • I. I would then define a plan of enterprise architecture work to meet the scope in the desired time line and the resources required and secure the support of stakeholders.
  • J. I would start by ensuring there is a Request for Architecture Work from the sponsor (the CIO). I would then create a project to define and deliver the architecture vision and the necessary output
  • K. The outputs include an approved Statement of Architecture Work, refined statements of Businesses Principles, Business Goals and Business Drivers, Architecture Principles, a Capability Assessment, a Tailored Architecture Framework, an Architecture vision, a Communications pla
  • L. The Statement of Architecture Work needs to be clear on the scope of architectural work, the resources needed to complete the work and amount of time it would take to complete the work assuming the scope of architectural work is agreed and that all the resources required are availabl
  • M. The final step would be to agree the Statement of Architectural Work with stakeholders confirming the scope, schedule and confirming the availability of the necessary resources.
  • N. I would start by establishing the architecture project and follow the appropriate project management metho
  • O. I would identify stakeholders their concerns and business requirements then confirm and elaborate the business goals, business drivers and constraint
  • P. I would then evaluate the business capabilities and readiness for business transformation and define the scop
  • Q. I would then develop the architecture vision, define the target architecture value proposition, KPIs and identify and mitigate all risks associated with the transformation effor
  • R. Finally, I would develop an Enterprise Architecture Plan and Statement of Work and secure approval from the relevant stakeholders.
  • S. I would approach this by defining and establishing the architecture team and governanc
  • T. This would be followed by agreeing and establishing the architecture principle
  • . I would select and customize an architecture framework changing any terminology and selecting the right phases and customizing the structure of content and outputs from the chosen metho
  • . Finally I would select and implement and architecture tool
  • . The outputs from this work would include an Organization Model for EnterpriseArchitecture, a Tailored Architecture Framework including method and content, the Architecture Principles, an initial architecture repository, restatement or references to business principles, business goals and business driver, a request for architecture work and the governance framework.

Answer: A

NEW QUESTION 10
SureFlight Air Carrier has received approval for the acquisition of a regional carrier.
To integrate the new acquisition, a TOGAF based enterprise architecture program has been initiated. The CIO sponsors the activity supported by the Chief Architect.
In Phase A within the initial iteration the CIO wants to ensure that the architecture activities are recognized among the various stakeholders of the enterprise.
Refer to the scenario above
You are a consultant supporting the Chief Architect that should explain how to identify and engage the stakeholders at this stage of the program.
Identify the best answer accordingly to the TOGAF 9 guidelines. Choose one of the following answers

  • A. Using the business scenarios technique you would identify supporting and not supporting stakeholders.Then you would list the set of viewpoints that are addressing the stakeholder concerns andshare these with them.
  • B. You first priority is to communicate with the regional carrier stakeholders developing a CommunicationsPlan to share main features and discuss opportunities with them.
  • C. You conduct a pilot proof of concept during Phase A to demonstrate the technical feasibility to the stakeholders explaining the approach available from your preferred suppliers.
  • D. You identify all the main stakeholders on both the acquired carrier and the rest of the enterpris
  • E. Using a stakeholder map, you classify and record their power in relation to this activit
  • F. You then focus on implementing the relevant viewpoints that can address the concerns of every main stakeholder identified in the stakeholders map.

Answer: D

NEW QUESTION 11
Scenario:
Please read this scenario prior to answering the Question
You are the Lead Architect for a firm that manufactures ball bearings used in industrial equipment applications. They have manufacturing operations in several cities in the United States, Germany, and the United Kingdom.
The firm has traditionally allowed each manufacturing plant to drive its own production planning systems. Each plant has its own custom Materials Requirements Planning, Master Production Scheduling, Bill of Materials, and Shop Floor Control systems.
"Just In Time" manufacturing techniques are used to minimize wastes caused by excessive inventory and work in process. The increasingly competitive business environment has compelled the firm to improve its business capability to be more responsive to the needs of industrial customers. To support this capability, the firm has decided to implement an Enterprise Resource Planning (ERP) solution that will enable it to better coordinate its manufacturing capacity to match the demands for its products across all plants. In addition, there are also new European regulations coming into force to which their manufacturing processes must conform in the next six months.
As part of the implementation process, the Enterprise Architecture (EA) department has begun to implement an architecture process based on TOGAF 9. The CIO is the sponsor of the activity. The Chief Architect has directed that the program should include formal modeling using the Architecture Content Framework and the TOGAF Content Metamodel. This will enable support for the architecture tooling that the firm uses for its EA program.
The Chief Architect has stated that in order to model the complex manufacturing process it will be necessary to model processes that are event-driven. Also, in order to consolidate applications across several data centers it will be necessary to model the location of IT assets. In particular, the end goal is to have the single ERP application running in a single data center.
Currently the project is in the Preliminary Phase, and the architects are tailoring the Architecture Development Method (ADM) and Architecture Content Framework to fit into the corporate environment.
Refer to the Scenario
You have been asked to recommend a response to the Chief Architect's request to tailor the TOGAF Content Metamodel.
Based on TOGAF 9, which of the following is the best answer?

  • A. You recommend that the architecture team incorporate the Process Modeling and Infrastructure Consolidation extensions into their tailored Content Metamode
  • B. As the environment is process-centric this will enable them to model the manufacturing processes and store information to support regulatory complianc
  • C. It also includes views useful for managing the consolidation of applications into a single data center.
  • D. You recommend that the architecture team incorporate the Process Modeling and Governance extensions into their tailored Content Metamode
  • E. This is suitable as this is a significant IT change that will impact its operational model
  • F. This will ensure that they include specific entities and attributes that will allow them to model the event-driven nature of the manufacturing processes more precisely.
  • G. You recommend that the architecture team incorporates the Governance and Motivation Extensions into their tailored Content Metamode
  • H. This would allow modeling of the target milestones they want to achieve with this consolidation of application to a single data cente
  • I. These extensions will also enable demonstration of regulatory compliance for the manufacturing process.
  • J. You recommend that the architecture team incorporates the Data and Services Extensions into their tailored Content Metamode
  • K. This would allow modeling of the location of IT assets and ensure regulatory compliance for the manufacturing proces
  • L. It will also allow for identification of redundant duplication of capability which will be needed for a successful consolidation to a single data center.

Answer: A

NEW QUESTION 12
Scenario: Vittronics Ltd.
Please read this scenario prior to answering the question
Vittronics Ltd. is a leading medical device manufacturer in the highly competitive market for Migraine Headache Pain Management (MHPM) devices. These tiny wireless devices are implanted in the brain and can deliver a precise electric shock when the wearable Pain Control Unit (PCU) detects an increase in stress induced by the onset of a migraine headache.
This technology will be a breakthrough in the treatment of this condition, and several competitors are striving to be the first to introduce a product into the market. However, all of them must demonstrate the effectiveness and safety of their products in a set of clinical trials that will satisfy the regulatory requirements of the countries in the target markets.
The Enterprise Architecture group at Vittronics has been engaged in an architecture development project to create a Secure Private Immersive Collaborative Environment (SPICE) that will allow researchers at its product development laboratories worldwide to share information about their independent clinical trials.
The Vittronics Enterprise Architecture group is a mature organization that has been utilizing
TOGAF for several years. They have recently upgraded to TOGAF 9. The Vittronics Architecture Development Method (VADM) is strictly based on the TOGAF 9 Architecture Development Method (ADM) with extensions required to support current good manufacturing practices and good laboratory practices in their target markets.
The SPICE project team has now completed the Business, Information Systems, and Technology Architecture phases and has produced a complete set of deliverables for each phase. Due to the highly sensitive nature of the information that is managed in SPICE, special care was taken to ensure that each architecture domain included an examination of the security and privacy issues that are relevant for each domain. A corresponding SPICE Security Architecture has been defined.
The Executive Vice President for Clinical Research is the sponsor of the Enterprise Architecture activity. He has stated that the changes to the SPICE architecture will need to be rolled out on a geographic basis that will minimize disruptions to ongoing clinical trials. The work will need to be done in stages and rolled out in geographical regions.
Refer to the Vittronics Ltd Scenario
You are serving as the Lead Architect for the SPICE project team.
You have been asked to recommend the approach to identify the work packages that will be included in the Transition Architecture(s).
Based en TOGAF 9, which of the following is the best answer?

  • A. Create an Implementation Factor Assessment and Deduction Matrix and a Consolidated Gaps, Solutions and Dependencies Matri
  • B. For each gap, identify a proposed solution and classify it as new development, purchased solution, or based on an existing produc
  • C. Group similar solutions together to form work package
  • D. Identify dependencies between work packages factoring in the clinical trial schedule
  • E. Regroup the packages into a set of Capability Increments scheduled into a series of Transition Architectures and documented in an Architecture Definition Increments Table.
  • F. Determine the set of Solution Building Blocks required by identifying which Solution Building Blocks need to be developed and which need to be procure
  • G. Eliminate any duplicate building block
  • H. Group the remaining Solution Building Blocks together to create the work packages using a CRLO matri
  • I. Rank the work packages in terms of cost and select the most cost-effective options for inclusion in a series of Transition Architecture
  • J. Schedule the roll out of the work packages to be sequential across the geographic regions.
  • K. Use a Consolidated Gaps, Solutions and Dependencies Matrix as a planning too
  • L. For each gap classify whether the solution is either a new development, purchased solution, or based on an existing produc
  • M. Group the similar solutions together to define the workpackage
  • N. Regroup the work packages into a set of Capability Increments to transition to the Target Architecture taking into account the schedule for clinical trials.
  • O. Group the Solution Building Blocks from a Consolidated Gaps, Solutions and Dependencies Matrix into a set of work package
  • P. Using the matrix as a planning tool, regroup the work packages to account for dependencie
  • Q. Sequence the work packages into the Capability Increments needed to achieve the Target Architectur
  • R. Schedule the rollout one region at a tim
  • S. Document the progression of the enterprise architecture using an Enterprise Architecture State Evolution table.

Answer: A

NEW QUESTION 13
Scenario: St. Croix Consulting
Please read this scenario prior to answering the question
St. Croix Consulting started as an accounting and financial services company. It has expanded over the years and is now a leading North American IT and Business Services provider.
With numerous practice areas and a multitude of diverse engagements underway at any given time, overall engagement management has become challenging. The company does not want to risk its outstanding reputation or its international certifications and CMM ratings. Senior partners must become team players, working to support the broader needs of the company and its shareholders.
The Enterprise Architecture team has been working to create St. Croixs Enterprise Architecture framework to address these issues. The team has defined a preliminary framework and held workshops with key stakeholders to define a set of principles to govern the architecture work. They have completed an Architecture Vision at a strategic level and laid out Architecture Definitions for the four domains. They have set out an ambitious vision of the future of the company over a five-year period.
An Architecture Review Board has been formed comprised of IT staff executives and executives from the major practice areas.
The Enterprise Architecture framework is based on TOGAF 9.
The Chief Executive Officer and Chief Information Officer have co-sponsored the creation of the Enterprise Architecture program.
Refer to the St Croix Consulting Scenario:
You have been assigned to the role of Chief Enterprise Architect.
As the EA team prepares to formulate an Implementation plan, they have been asked by the CIO to assess the risks associated with the proposed architecture. He has received concerns from senior management that the proposed architecture may be too ambitious and they are not sure it can produce sufficient value to warrant the attendant risks.
You have been asked to recommend an approach to satisfy these concerns. Based on TOGAF 9, which of the following is the best answer?

  • A. An interoperability analysis should be applied to evaluate any potential issues across the Solution Architectur
  • B. Once all of the concerns have been resolved, the EA team shouldfinalize the Architecture Implementation Roadmap and the Migration Plan.
  • C. The EA team should gather information about potential solutions from the appropriate source
  • D. Once the Solution Architecture has been assembled, it should be analyzed using a state evolution table to determine the Transition Architectures.
  • E. Prior to preparing the Implementation plan, the EA team should create a consolidated gap analysis to understand the transformations that are required to achieve the proposed Target Architectur
  • F. The EA team should gather information about potential solutions from the appropriate source
  • G. Once the Solution Architecture has been assembled, it should be analyzed using a state evolution table to determine the Transition Architecture
  • H. An interoperability analysis should be applied to evaluate any potential issues across the Solution Architecture.
  • I. Prior to preparing the Implementation plan, there are several techniques that should be applied to assess the risks and value of the proposed transformatio
  • J. In particular, the EA team should pay attention to the Business Transformation Readiness Assessment and the Business Value Assessment.

Answer: C

NEW QUESTION 14
Scenario: Eight Twelve
Eight Twelve has retail outlets throughout North America. An Enterprise Architecture practice already exists in Eight Twelve. Now the CEO and CIO decide that they want to use TOGAF9 to re-architect their Enterprise Architecture to cater to the changing strategies of Eight Twelve to better respond to the changes in the economic and technology environments.
Some of the key issues which need to be addressed in this re-architecting work are:
1. Since Eight Twelve’s retail chain operate 24 hours a day and are expanding to South America and Europe, the retail chain business ecosystem should be able to withstand any unforeseen disruptions which might affect the chain’s day to day operations. This is highly critical to ensure high levels of customer satisfaction and thus maintaining and enhancing Eight Twelve’s revenue chain.
2. Dependency between the application components, which are the nerve centers to Eight Twelve’s sophisticated range of services both external and internal, and the application platform and technology infrastructure should be minimal. This would facilitate scalability and ease of enhancement of the service offerings.
3. Eight Twelve uses the ARTS Data Model and the quality of data is of utmost importance for its operation.
4. Users of the Enterprise Information ecosystem should have an environment which is able to cater to their needs without any undue delays.
Which one of the following set of Architecture Principles do you feel is the most appropriate for these guidelines stated above for the TOGAF 9 architecting work which Eight Twelve is embarking on?

  • A. a) Maximize Benefit to the Enterprise b).Data Trusteec) Service Orientationd) Responsive Change Management
  • B. a) Business Continuity b).Data is an Assetc) Data is Sharedd) Requirements Based Change
  • C. a) Maximize Benefit to the Enterprise b).Data is an Assetc) Data is Sharedd) Requirements Based Change
  • D. a) Business Continuity b).Data Trusteec) Technology Independenced) Responsive Change Management

Answer: D

NEW QUESTION 15
Scenario: Rollins Manufacturing
Please read this scenario prior to answering the question
Rollins Manufacturing is a major supplier in the automotive industry, headquartered in Cleveland, Ohio with manufacturing plants in Chicago, Sao Paulo, Stuttgart, Yokohama, and Seoul. Each of these plants has been operating its own Manufacturing Requirements Planning (MRPII) system, production scheduling, and custom developed applications that drive the automated production equipment at each plant.
Rollins is implementing lean manufacturing principles to minimize waste and improve the efficiency of all of its production operations. During a recent exercise held for internal quality improvement, it was determined that a significant reduction in process waste could be achieved by replacing the current MRPII and scheduling systems with a common Enterprise Resource Planning (ERP) system located in the Cleveland data center. This central system would provide support to each of the plants replacing the functionality in the existing systems. It would also eliminate the need for full data centers at each of the plant facilities. A reduced number of IT staff could support the remaining applications. In some cases, a third-party contractor could provide those staff.
The Rollins Enterprise Architecture department has been operating for several years and
has mature, well-developed architecture governance and development processes that are strongly based on TOGAF 9.At a recent meeting, the Architecture Review Board approved a Request for Architecture Work from the Chief Engineer of Global Manufacturing Operations who is the project sponsor. The request covered the initial architectural investigations and the development of a comprehensive architecture to plan the transformation.
The Common ERP Deployment architecture project team has now been formed, and the project team has been asked to develop an Architecture Vision that will achieve the desired outcomes and benefits. Some of the plant managers have expressed concern about the security and reliability of driving their MRPII and production scheduling from a central system located in Cleveland. The Chief Engineer wants to know how these concerns can be addressed.
Refer to the Rollins Manufacturing Scenario:
You are serving as the Lead Enterprise Architect for the Common ERP Deployment architecture project.
One of the earliest initiatives in the Enterprise Architecture program at Rollins was the definition of a set of IT principles and architecture principles that are well aligned with the overall enterprise principles. These now need to be updated to address the concerns raised.
You have been asked to select a set of principles most appropriate for guiding the team to define a robust solution.
[Note: You should assume that Rollins has adopted the example set of principles that are listed and defined in TOGAF 9, Section 23.6.]
Based on TOGAF 9, which of the following is the best answer?

  • A. Common-use Applications, Data is Shared, Data is Accessible, Data is Secure, Interoperability, Control Technical Diversity.
  • B. Business Continuity, Service-orientation, Data is Accessible, Data is Secure, Responsive Change Management.
  • C. Maximize Benefit to the Enterprise, Business Continuity, Common-use Applications, Data is Shared, Data is Accessible, Data is Secure.
  • D. Information Management is Everybody's Business, IT Responsibility, Data Trustee, Technology Independence, Responsive Change Management.

Answer: C

NEW QUESTION 16
......