OG0-093 Exam - OG0-093 TOGAF 9 Combined Part 1 and Part 2

certleader.com

Q1. Scenario: MedInc Products Ltd. 

Please read this scenario prior to answering the Question. 

MedInc Products Ltd. is a leading medical device manufacturer in the highly competitive market for Migraine Headache Pain Management (MHPM) devices. These tiny wireless devices are implanted in the brain and can deliver a precise electric shock when the wearable Pain Control Unit (PCU) detects an increase in stress induced by the onset of a migraine headache. This technology will be a breakthrough in the treatment of this condition, and several competitors are striving to be the first to introduce a product into the market. However, all of them must demonstrate the effectiveness and safety of their products in a set of clinical trials that will satisfy the regulatory requirements of the countries in the target markets. 

The Enterprise Architecture group at MedInc Products has been engaged in an architecture development project to create a secure networked collaboration system that will allow researchers at its product development laboratories worldwide to share information about their independent clinical trials. The Enterprise Architecture group is a mature organization that has been utilizing TOGAF for several years. The MedInc Architecture Development Method is strictly based on TOGAF 9 with extensions required to support current good manufacturing practices and good laboratory practices in their target markets. The project team has now completed the Business, Information Systems, and Technology Architecture phases and has produced a complete set of deliverables for each phase. Due to the highly sensitive nature of the information that is managed, special care was taken to ensure that each architecture domain included an examination of the security and privacy issues that are relevant for each domain. A corresponding Security Architecture has been defined. 

The Executive Vice President for Clinical Research is the sponsor of the Enterprise Architecture activity. He has stated that the changes to the enterprise architecture for the new system will need to be rolled out on a geographic basis that will minimize disruptions to ongoing clinical trials. The work will need to be done in stages and rolled out in geographical regions. 

Refer to the Medlnc Products Ltd. Scenario 

You are serving as the Lead Architect for the project team. 

You have been asked to recommend the approach to identify the work packages that will be included in the Transition Architecture(s). 

Based on TOGAF 9, which of the following is the best answer? 

A. Create an Implementation Factor Assessment and Deduction Matrix and a Consolidated Gaps, Solutions and Dependencies Matrix. For each gap, identify a proposed solution and classify it as new development, purchased solution, or based on an existing product. Group similar solutions together to form work packages. Identify dependencies between work packages factoring in the clinical trial schedules. Regroup the packages into a set of Capability Increments scheduled into a series of Transition Architectures and documented in an Architecture Definition Increments Table. 

B. Determine the set of Solution Building Blocks required by identifying which Solution Building Blocks need to be developed and which need to be procured. Eliminate any duplicate building blocks. Group the remaining Solution Building Blocks together to create the work packages using a CRUD matrix. Rank the work packages in terms of cost and select the most cost-effective options for inclusion in a series of Transition Architectures. Schedule the roll out of the work packages to be sequential across the geographic regions. 

C. Use a Consolidated Gaps, Solutions and Dependencies Matrix as a planning tool. For each gap classify whether the solution is either a new development, purchased solution, or based on an existing product. Group the similar solutions together to define the work packages. Regroup the work packages into a set of Capability Increments to transition to the Target Architecture taking into account the schedule for clinical trials. 

D. Group the Solution Building Blocks from a Consolidated Gaps, Solutions and Dependencies Matrix into a set of work packages. Using the matrix as a planning tool, regroup the work packages to account for dependencies. Sequence the work packages into the Capability Increments needed to achieve the Target Architecture. Schedule the rollout one region at a time. Document the progression of the enterprise architecture using an Enterprise Architecture State Evolution table. 

Answer:

Explanation: 

Q2. In Phases B, C, and D which is the final step in each phase? 

A. Conduct formal stakeholder review 

B. Create Architecture Definition Document 

C. Define Roadmap components 

D. Perform gap analysis 

E. Select reference models, viewpoints and tools 

Answer:

Explanation: 

Q3. Scenario: Reveille Bugle 

Please read this scenario prior to answering the question 

For over 100 years, Reveille Bugle has been manufacturing brass bugles and other musical instruments. North America has been the primary market for Reveille's products. However, the firm has now expanded into European markets and will soon establish a market in Latin America. A future expansion into the Asia Pacific region is also planned. 

The firm is organized into several business units that each focus on manufacturing particular families of instruments such as brass, woodwind, and percussion. Each business unit has acquired other producers to create its manufacturing capacity. This has resulted in a complex environment with a high diversity of business and manufacturing systems. 

The Enterprise Architecture (EA) program at Reveille Bugle has been functioning for several years. It has made significant progress in consolidating the technology portfolio and establishing key standards. The CIO and the COO are joint sponsors of the EA program. By all measures, the EA program is mature, with an active Architecture Board and a well-defined architecture process and standard content templates based on the TOGAF 9 Architecture Content Framework. The EA process framework is well coordinated with the PMO, Systems Development, and Operations functions. 

The firm has completed a strategic plan to reorganize its Sales & Marketing organization according to four geographic market sectors: North America; Europe, Africa, and Middle East; Latin America; and Asia-Pacific. One of the goals of this reorganization is to improve the ability of Marketing to collect more meaningful market analytics that will enable each sector to better address market needs with effective marketing campaigns and global product presence. 

A Request for Architecture Work has been approved. As the architecture team commences its work, the CIO has expressed a concern about whether the firm will be able to adapt to the proposed architecture and how to manage the associated risks. 

Refer to the Reveille Bugle Scenario 

Your role is consultant to the Lead Architect. 

You have been asked how to address the concerns of the CIO. 

Based on TOGAF 9, which of the following is the best answer? 

A. In Phase A, the team should conduct a Business Scenario to identify the stakeholders' concerns and the resulting requirements. Once the requirements have been identified, they can be assessed in terms of their risks. The risks should be evaluated in terms of how they could be avoided, transferred, or mitigated. Any risks that cannot be resolved should be identified as residual risks and their disposition should be decided by the Architecture Board. 

B. In Phase A, the team should use the Business Transformation Readiness Assessment technique to identify the factors that will influence the successful introduction of the architecture into the organization. The assessment should include determining the readiness rating for each factor based on a maturity scale that will allow the team to gauge the urgency, readiness, and degree of difficulty to fix. These factors can then used to assess the initial risks associated with the proposed architecture. 

C. In Phase A the team should analyze their risk by completing an Implementation Factor Assessment and Deduction Matrix to identify the particular risks associated with the implementation and deployment. These factors can then used to assess the initial risks associated with the proposed architecture. 

D. In Phase B, the team should create a set of views and viewpoints that will enable them to identify the factors that will influence the successful introduction of the architecture into the organization. There should then be an assessment of each factor on a maturity scale that will allow the team to gauge the urgency, readiness, and degree of difficulty to fix. These factors can then be used to assess the initial risks associated with the proposed architecture. 

Answer:

Explanation: 

Q4. Scenario 

Please read this scenario prior to answering the question Your role is that of the Lead Architect working for a government agency responsible for immigration, customs, and border control. The agency was formed by consolidating several smaller government agencies. The agency has established an Enterprise Architecture practice based on TOGAF 9. The CIO is the executive sponsor and has appointed an EA steering team to oversee the practice. 

There has been a considerable increase in security requirements and immigration service requests in recent years, which have expanded the scope and size of the operations of the agency. As a result, the existing Information Technology architecture no longer meets the required service levels. A significant Enterprise Architecture (EA) initiative is in progress with the opal to improve customer responsiveness and satisfaction, and improve the overall operational efficiency of the agency. 

The current EA staff members were internal appointments based on a request from the EA steering team to supply a number of suitable individuals for the EA effort. Collectively, they possess a broad range of IT and business analysis skills. However, the CIO has expressed concern about the diverse range of experience within the team. There is concern that the EA staff may be lacking in some of the critical skills that are required to properly conduct EA activities. It had been assumed that any EA-related skill gaps would be overcome by on-the-job mentoring from the senior members of the EA staff. Each architect was expected to attend a TOGAF training course and participate in other skill development activities. 

A recent review of the EA program revealed that many EA staff members, despite attending multi-day training courses, were not proficient in analyzing or creating the models and artifacts required for their assigned architecture projects. Stakeholders have observed errors and inconsistencies in artifacts and deliverables being submitted for review. 

Refer to the Scenario 

The CIO has asked you to recommend a professional development plan for the EA staff in order to address the findings raised in the recent review. 

Based on TOGAF, which of the following is the best answer? 

A. You recommend that a comprehensive evaluation of key team leader skills be made using the TOGAF Architecture Skills Framework. Based on the evaluations, you will recommend the necessary staff changes. This will ensure that the team leaders have the necessary skills and experience for the architecture tasks within the agency. The role and skill categories defined in the TOGAF Architecture Skills Framework should then be shared with the department leaders so that in the future, they can make more informed choices when providing internal candidates for the EA team. 

B. You recommend that an architecture maturity assessment should be conducted. This will identify the practices on which the agency should focus to see the greatest improvement and ensure that the basic enterprise architecture process is documented. As part of the assessment, all of the team leaders should be interviewed and their qualifications assessed. In order to rectify areas of low proficiency, they are expected to attend additional EA training courses. When the team leaders have achieved the desired levels of proficiency, they should apply a similar process for their staff members. 

C. You recommend that you work with the EA steering team to adapt the TOGAF Architecture Skills Framework for use within the architecture practice at the agency. The categories of architecture roles, the required skills for each role and the desired level of proficiency for each role and skill will be defined by this framework. Each team member, or prospective team member, can then be evaluated for suitability against these roles and skills. Staffing and training adjustments can then be made as necessary to close gaps that are discovered. 

D. You recommend that to address the issues identified in the review, the experienced team leaders should mentor the junior team members. At the same time additional training should be provided. Since it is now known that some models are improperly defined and may have caused cascading errors in other parts of the architecture, you recommend an iteration of the Migration Planning phase occur, so as to develop a coordinated transition to a new baseline using the last known good architecture. Once the artifacts are consistent and correct, these can be applied to this new baseline. 

Answer:

Explanation: 

Q5. Complete the sentence. TOGAF covers the development of four architecture domains, Business, Data, Technology and ___________. 

A. Application 

B. Capability 

C. Segment 

D. Transition 

E. Vision 

Answer:

Explanation: 

Q6. Scenario: Mobile Telco 

Please read this scenario prior to answering the Question. 

Mobile Telco is a mobile telecommunications company formed through a series of mergers and acquisitions. They are yet to fully integrate the customer service systems for the most recent acquisitions, and as result, customer service has been a major concern for the Chief Technology Officer. Results for the last two quarters have shown that Average Revenue Per User (ARPU) and the customer retention (Churn) rate have fallen below the industry average. 

The Corporate Marketing group has published some new findings about customer satisfaction. The customers appear to be switching to AirLight, a competitor, because of superior customer service. Mobile Telco actually has better coverage in nearly all markets than AirLight, and good roaming agreements that keep rates low for business travelers. But, customer satisfaction has remained low. The Business Strategy group and the Enterprise Architecture group have conducted a high-level project to develop the enterprise-wide strategic plan. 

They have developed a business scenario which contains a good conceptual model of what needs to be done, and also identifies the key requirements. This was used in preparing the proposal presented to the Executive Council and the Corporate Board. The planning for the program has been underway for several months. Mobile Telco has selected TOGAF 9 as the basis for its Enterprise Architecture. The Corporate Board has approved funding for a multi-million Euro conversion to transition to a packaged Customer Service System. It is anticipated that the overall program will take five years to complete, but there are some tactical projects that can commence immediately to address the situation. 

The Executive Council has stated that the program should define specific initiatives to enable each regional business unit to create an implementation of the Customer Service System. The implementation must meet the needs of the business unit and still provide the information needed to enable major improvements to the customer. 

Refer to the Mobile Telco Scenario 

You are serving as the Lead Architect for the Performance and Integrity project of the Customer Service System program. 

The project has been chartered to address the architecture(s) required to support the Customer Service System from an infrastructure perspective. At the present time, the project team is conducting an architecture development project that is focused on the customer self-service capability, which was defined as part of the earlier strategic planning activities. This capability will enable customers to access their accounts, pay bills, request account reviews, and provision services from any web-enabled device. 

The project team has gathered information about the self-service capability, developed a business scenario, and used the results to define an Architecture Vision for achieving the capability. 

You have been asked to recommend the course of action to complete the project. 

Based on TOGAF 9, which of the following is the best answer? 

A. In the remaining architecture definition phases, the project team should map out the capability in the Technology domain. In Phases E and F, the capability should be broken down into a set of Solution Building Blocks that define the Target Architecture. Where possible, the Solution Building Blocks should be drawn from the Architecture Repository. The completed Architecture Definition Document and the Implementation and Migration Plan will be submitted for approval. Upon approval, the architecture team will conduct Compliance Assessments to ensure that the Target Architecture is properly implemented. 

B. In the remaining architecture definition phases, the project team should map out the capability across the Business, Information Systems, and Technology domains. In Phases E and F, the capability should be broken down into a set of increments that are sequenced into Transition Architectures that will lead to the realization of the Target Architecture. The resulting Solution Building Blocks will then provide the basis for the capability increment solutions. The completed Architecture Definition Document and the implementation end Migration Plan will be submitted for approval. Upon approval, the architecture team will oversee the implementation process through monitoring Architecture Contracts and by conducting Compliance Assessments. 

C. In the remaining architecture definition phases, the project team should map out the capability across the Business, Information Systems, and Technology domains. In Ftiases E and F, the capability should be broken down into a set of increments that define the Target Architecture. The resulting Solution Building Blocks will provide the basis for tne capability increment solutions. The completed Architecture Definition Document and the Implementation and Migration Plan will be submitted for approval. Upon approval, the architecture team will oversee the implementation process through monitoring Architecture Contracts and by conducting Compliance Assessments. 

D. The remaining architecture definition work should be focused en mapping out the technology and infrastructure capability in the Technology domain. In Phases E and F, the capability should be broken down into a set of Solution Building Blocks that will be implemented to realize the Target Architecture. The Solution Building Blocks will provide the basis for the completed Architecture Definition Document that will be submitted for approval. Upon approval, the implementation team will conduct Compliance Assessments to ensure that the self-service capability is compliant with the overall Enterprise Architecture. 

Answer:

Explanation: 

Q7. Complete the sentence. TOGAF defines five criteria for a good set of principles: Complete, Consistent, Stable, Understandable and_______. 

A. Agile, 

B. Dynamic 

C. Comprehensive 

D. Robust 

E. Strategic 

Answer:

Explanation: 

Q8. Which of the following best describes the class of information known as the Reference Library within the Architecture Repository? 

A. A description of the organization specific architecture framework and method 

B. A record of the governance activity across the enterprise 

C. Guidelines and templates used to create new architectures 

D. Processes to support governance of the Architecture Repository 

E. Specifications to which architectures must conform 

Answer:

Explanation: 

Q9. In which section of the TOGAF template for Architecture Principles would a reader find the answer to the QUESTION NO: of 'How does this affect me"? 

A. Implications 

B. Name 

C. Rationale 

D. Statement 

Answer:

Explanation: 

Q10. Scenario: 

Please read this scenario prior to answering the Question 

You are serving as the Lead Architect for an enterprise architecture project team within a leading medical device manufacturer that specializes in miniature devices. The latest product under development is a tiny wireless device that can be implanted in the brain and can deliver a precise electric shock when the wearable Pain Control Unit (PCU) detects an increase in stress induced by the onset of a migraine headache. 

This technology will be a breakthrough in the treatment of this condition, and several competitors are striving to be the first to introduce a product into the market. However, all of them must demonstrate the effectiveness and safety of their products in a set of clinical trials that will satisfy the regulatory requirements of the countries in the target markets. 

The Enterprise Architecture group within the company has been engaged in an architecture development project to create a secure networked collaboration system that will allow researchers at its product development laboratories worldwide to share information about their independent clinical trials. 

The Enterprise Architecture group is a mature organization that has been utilizing TOGAF for several years. They use the TOGAF 9 ADM with extensions required to support current good manufacturing practices and good laboratory practices in their target markets. Due to the highly sensitive nature of the information that is managed, special care was taken to ensure that each architecture domain included an examination of the security and privacy issues that are relevant for each domain. A corresponding Security Architecture has been defined. 

The Executive Vice President for Clinical Research is the sponsor of the Enterprise Architecture activity. She has stated that the changes to the enterprise architecture for the new system will need to be rolled out on a geographic basis that will minimize disruptions to ongoing clinical trials. The work will need to be done in stages and rolled out in geographical regions. 

Refer to the Scenario 

You have been asked to recommend the approach to identify the work packages that will be included in the Transition Architecture(s). 

Based on TOGAF 9, which of the following is the best answer? 

A. Determine the set of Solution Building Blocks required by identifying which Solution Building Blocks need to be developed and which need to be procured. Eliminate any duplicate building blocks. Group the remaining Solution Building Blocks together to create the work packages using a CRUD matrix. Rank the work packages in terms of cost and select the most cost-effective options for inclusion in a series of Transition Architectures. Schedule the roll out of the work packages to be sequential across the geographic regions. 

B. Create an Implementation Factor Assessment and Deduction Matrix and a Consolidated Gaps, Solutions and Dependencies Matrix. For each gap, identify a proposed solution and classify it as new development, purchased solution, or based on an existing product. Group similar solutions together to form work packages. Identify dependencies between work packages factoring in the clinical trial schedules. Regroup the packages into a set of Capability Increments scheduled into a series of Transition Architectures. 

C. Group the Solution Building Blocks from a Consolidated Gaps, Solutions and Dependencies Matrix into a set of work packages. Using the matrix as a planning tool, regroup the work packages to account for dependencies. Sequence the work packages into the Capability Increments needed to achieve the Target Architecture. Schedule the rollout one region at a time. 

Document the progression of the enterprise architecture using a state evolution table. 

D. Use a Consolidated Gaps, Solutions and Dependencies Matrix as a planning tool. For each gap classify whether the solution is either a new envelopment, purchased solution, or based on an existing product. Group the similar solutions together to define the work packages. Regroup the work packages into a set of Capability Increments to transition to the Target Architecture taking into account the schedule for clinical trials. 

Answer:

Explanation: