Your success in PMP PMP is our sole target and we develop all our PMP braindumps in a way that facilitates the attainment of this target. Not only is our PMP study material the best you can find, it is also the most detailed and the most updated. PMP Practice Exams for PMP PMP Certification PMP are written to the highest standards of technical accuracy.

Online PMP free questions and answers of New Version:

NEW QUESTION 1

Verification of project deliverables occurs during which process?

  • A. Develop preliminary project scope statement
  • B. Close Project or Phase
  • C. Develop project charter
  • D. Create WBS

Answer: B

NEW QUESTION 2

Which technique is commonly used for the Perform Quantitative Risk Analysis process?

  • A. Brainstorming
  • B. Strategies for opportunities
  • C. Decision tree analysis
  • D. Risk data quality assessment

Answer: C

NEW QUESTION 3

The Cost Management processes and their associated tools and techniques are usually selected during which of the following?

  • A. Project finance management
  • B. Project cost estimation
  • C. Project life cycle definition
  • D. Project plan development

Answer: C

NEW QUESTION 4

The following is a network diagram for a project.
PMP dumps exhibit
The free float for Activity H is how many days?

  • A. 4
  • B. 5
  • C. 10
  • D. 11

Answer: A

NEW QUESTION 5

Which type of graphic is displayed below?
PMP dumps exhibit

  • A. Work breakdown structure
  • B. Context diagram
  • C. Control chart
  • D. Pareto diagram

Answer: A

NEW QUESTION 6

The process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule is known as:

  • A. Plan Schedule Management.
  • B. Develop Project Charter.
  • C. Develop Schedule.
  • D. Plan Scope Management.

Answer: A

NEW QUESTION 7

In Project Cost Management, which input is exclusive to the Determine Budget process?

  • A. Scope baseline
  • B. Organizational process assets
  • C. Project schedule
  • D. Resource calendars

Answer: D

NEW QUESTION 8

Risk exists the moment that a project is:

  • A. planned.
  • B. conceived.
  • C. chartered.
  • D. executed.

Answer: B

NEW QUESTION 9

Which cost is associated with nonconformance?

  • A. Liabilities
  • B. Inspections
  • C. Training
  • D. Equipment

Answer: A

NEW QUESTION 10

Which of the following is an input to the Develop Project Charter process?

  • A. Work performance information
  • B. Project management plan
  • C. Business case
  • D. Change requests

Answer: C

NEW QUESTION 11

Which Control Scope input is compared to actual results to determine if corrective action is required for the project?

  • A. Scope baseline
  • B. Scope management plan
  • C. Change management plan
  • D. Cost baseline

Answer: A

NEW QUESTION 12

Assigned risk ratings are based upon:

  • A. Root cause analysis.
  • B. Risk probability and impact assessment.
  • C. Expert judgment.
  • D. Revised stakeholders' tolerances.

Answer: B

NEW QUESTION 13

What is the probability of occurrence if the risk rating is 0.56 and the impact if the risk does occur is very high (0.80)?

  • A. 0.45
  • B. 0.56
  • C. 0.70
  • D. 1.36

Answer: C

NEW QUESTION 14

What is the risk rating if the probability of occurrence is 0.30 and the impact if it does occur is moderate (0.20)?

  • A. 0.03
  • B. 0.06
  • C. 0.10
  • D. 0.50

Answer: B

NEW QUESTION 15

Sending letters, memos, reports, emails, and faxes to share information is an example of which type of communication?

  • A. Direct
  • B. Interactive
  • C. Pull
  • D. Push

Answer: D

NEW QUESTION 16

Which of the following is a schematic display of the project’s schedule activities and the logical relationships among them?

  • A. Gantt chart
  • B. Project schedule network diagram
  • C. Project milestone list
  • D. Activity list

Answer: B

NEW QUESTION 17

PMP dumps exhibit
Which of the following is the correct network diagram for the table?

  • A. Begin-A-C-D-E-End-B-D
  • B. Begin-A-B-C-D-E-End
  • C. Begin-A-B-D-E-End A-C-D
  • D. Begin-A-C-D-E-End-B-C

Answer: A

NEW QUESTION 18

What is the responsibility of the project manager and the functional manager respectively?

  • A. Oversight for an administrative area; a facet of the core business
  • B. Achieving the project objectives; providing management oversight for an administrative area
  • C. A facet of the core business; achieving the project objectives
  • D. Both are responsible for achieving the project objectives.

Answer: B

NEW QUESTION 19

Which of the following is developed from the project scope baseline and defines only that portion of the project scope that is to be included within a related contract?

  • A. Product scope description
  • B. Procurement statement of work
  • C. Project schedule
  • D. Work breakdown structure (WBS)

Answer: B

NEW QUESTION 20

While preparing the project management plan on a weekly basis, the project manager indicates the intention to provide an issues report to the staff via e-mail. In which part of the plan will this type of information be included?

  • A. Communications management plan
  • B. Human resource plan
  • C. Quality management plan
  • D. Procurement management plan

Answer: A

NEW QUESTION 21

What type of project structure is a hierarchically organized depiction of the resources by type?

  • A. Organizational breakdown structure (OBS)
  • B. Resource breakdown structure (RBS)
  • C. Work breakdown structure (WBS)
  • D. Project breakdown structure (PBS)

Answer: B

NEW QUESTION 22

Activity cost estimates and the project schedule are inputs to which Project Cost Management process?

  • A. Estimate Costs
  • B. Control Costs
  • C. Plan Cost Management
  • D. Determine Budget

Answer: D

NEW QUESTION 23

Organizational process assets can be divided into which of the following two categories?

  • A. Project files and corporate knowledge base
  • B. Templates, and processes and procedures
  • C. Standards, and processes and procedures
  • D. Corporate knowledge base and processes and procedures

Answer: D

NEW QUESTION 24

Which of the following is an input of the Define Activities process?

  • A. Scope baseline
  • B. Milestone list
  • C. Resource calendars
  • D. Activity list

Answer: A

NEW QUESTION 25

Within project integration management, the statement of work (SOW) references which aspects of the project?

  • A. Strategic plan, business need, and product scope description
  • B. Contract, enterprise environmental factors, and organizational process assets
  • C. Business plan, project management plan, and project schedule
  • D. Product lifecycle, business objective, and management strategy

Answer: A

NEW QUESTION 26

Which defines the portion of work included in a contract for items being purchased or acquired?

  • A. Procurement management plan
  • B. Evaluation criteria
  • C. Work breakdown structure
  • D. Procurement statement of work

Answer: D

NEW QUESTION 27
......