we provide Refined PMP PMP practice exam which are the best for clearing PMP test, and to get certified by PMP Project Management Professional. The PMP Questions & Answers covers all the knowledge points of the real PMP exam. Crack your PMP PMP Exam with latest dumps, guaranteed!
Also have PMP free dumps questions for you:
NEW QUESTION 1
Which risk response strategy is common for both positive and negative risks?
Answer: B
NEW QUESTION 2
Which of the following forecasting methods uses historical data as the basis for estimating future outcomes?
Answer: A
NEW QUESTION 3
The Plan Procurements process includes documenting project purchasing decisions and what other steps?
Answer: A
NEW QUESTION 4
Which is a communication method used in the Report Performance process?
Answer: D
NEW QUESTION 5
What is an objective of the Develop Project Team process?
Answer: A
NEW QUESTION 6
A work package has been scheduled to cost $1,000 to complete and was to be finished today. As of today, the actual expenditure is $1,200 and approximately half of the work has
been completed. What is the cost variance?
Answer: A
NEW QUESTION 7
An example of a group decision-ma king technique is:
Answer: B
NEW QUESTION 8
What is a deliverable-oriented, hierarchical decomposition of the work to be executed to accomplish the project objectives and create the required deliverables?
Answer: D
NEW QUESTION 9
What is a tool and technique used in the Develop Project Management Plan process?
Answer: D
NEW QUESTION 10
Organizational process assets, a lessons-learned database, and historical information are all inputs to which process?
Answer: C
NEW QUESTION 11
A risk that arises as a direct result of implementing a risk response is called a:
Answer: D
NEW QUESTION 12
What risk technique is used to quantify the probability and impact of risks on project objectives?
Answer: D
NEW QUESTION 13
Which Knowledge Areas include processes from the Closing Process Group?
Answer: D
NEW QUESTION 14
Which is an enterprise environmental factor?
Answer: A
NEW QUESTION 15
Change requests are an output from which Project Integration Management process?
Answer: A
NEW QUESTION 16
What is the definition of Direct and Manage Project Execution?
Answer: B
NEW QUESTION 17
An input to the Estimate Activity Resources process is:
Answer: C
NEW QUESTION 18
Which project risk listed in the table below is most likely to occur?
Answer: B
NEW QUESTION 19
Risk responses reflect an organization's perceived balance between:
Answer: A
NEW QUESTION 20
At which stage of team development do members begin to work together, adjust work habits, and trust each other?
Answer: C
NEW QUESTION 21
Which of the following are inputs into the Administer Procurements process?
Answer: C
NEW QUESTION 22
A method of obtaining early feedback on requirements by providing a working model of the expected product before actually building is known as:
Answer: D
NEW QUESTION 23
......
Recommend!! Get the Full PMP dumps in VCE and PDF From Surepassexam, Welcome to Download: https://www.surepassexam.com/PMP-exam-dumps.html (New 918 Q&As Version)