PRINCE2-Foundation Exam - PRINCE2 Foundation exam

certleader.com

Q1. - (Topic 2) 

Which PRINCE2 principle is supported by the setting of tolerances for the three levels of plan? 

A. Manage by stages 

B. Manage by exception 

C. Continued business justification 

D. Learn from experience 

Answer:

Q2. - (Topic 2) 

During the Managing a Stage Boundary process what product is updated with estimated costs and time for the stage that is about to begin? 

A. End Stage Report 

B. Team Plan 

C. Work Package 

D. Project Plan 

Answer:

Q3. - (Topic 2) 

Which product identifies the management stages and timescales of a project? 

A. Project Brief 

B. Project Product Description 

C. Project Plan 

D. Initiation Stage Plan 

Answer:

Q4. - (Topic 1) 

Which should be funded from a change budget? 

A. The Starting up a Project process 

B. A fallback plan 

C. An agreed change to the scope of a project 

D. A change to a plan, within allocated tolerances, due to poor estimating 

Answer:

Q5. - (Topic 1) 

Which characteristic distinguishes a project from regular business operations? 

A. Produces benefits 

B. Introduces business change 

C. Manages stakeholders 

D. Incurs cost 

Answer:

Q6. - (Topic 1) 

Identify the missing words in the following sentence. A project is [ ? ] organization that is created for the purpose of delivering business products. 

A. a corporate 

B. a temporary 

C. an external 

D. a technical 

Answer:

Q7. - (Topic 1) 

Which is a benefit of using PRINCE2? 

A. Is a method specifically designed for technical projects 

B. Provides for the efficient and economic use of management time 

C. Includes many of the proven planning techniques, such as critical path analysis 

D. Can be used to manage both projects and programmes 

Answer:

Q8. - (Topic 2) 

Identify the missing word(s) in the following sentence. The Quality theme provides a set of rules and procedures which ensure that the [ ? ] created meet(s) the needs of the business. 

A. controls 

B. products 

C. project management team 

D. stages 

Answer:

Q9. - (Topic 1) 

In what process is the authorization to deliver the project's products given? 

A. Starting up a Project 

B. Initiating a Project 

C. Managing a Stage Boundary 

D. Directing a Project 

Answer:

Q10. - (Topic 1) 

What needs to be in place to ensure effective issue and change control? 

A. Configuration management system 

B. Manage by exception 

C. Quality planning 

D. Information needs for stakeholders 

Answer: