Q1. - (Topic 1)
Which product records any project outcomes perceived as negative by stakeholders?
A. Business Case
B. Project Plan
C. Communication Management Strategy
D. Project Product Description
Answer: A
Q2. - (Topic 1)
Which is a typical core activity within configuration management?
A. Quality assurance
B. Risk management
C. Verification and audit
D. Progress reporting
Answer: C
Q3. - (Topic 1)
Which is assumed to be a supplier's responsibility in the PRINCE2 customer/supplier environment?
A. Specify the desired result
B. Provide the resources and skills to deliver the desired result
C. Pay for the project
D. Specify the benefits of the project
Answer: B
Q4. - (Topic 1)
Which of the following statements about the Closing a Project process are true?
1.
The Closing a Project process provides a fixed point for the receipt of completed Work Packages for the work performed in the final stage.
2.
The Closing a Project process provides a fixed point to review if the objectives set out in the original Project Initiation Documentation have been achieved.
A. Only 1 is true
B. Only 2 is true
C. Both 1 and 2 are true
D. Neither 1 or 2 are true
Answer: B
Q5. - (Topic 2)
Which is a purpose of a Risk Register?
A. Capture risks that may occur during the project
B. Record how risk management activities will be undertaken on the project
C. Record the risk tolerance for the project
D. Capture issues which are impacting on the delivery of the project objectives
Answer: A
91. - (Topic 2)
Which process provides the Project Board with sufficient information for it to review the success of a completed stage and confirm continued business justification?
A. Controlling a Stage
B. Closing a Project
C. Directing a Project
D. Managing a Stage Boundary
Q6. - (Topic 2)
Which is a true statement about acceptance criteria?
A. Acceptance criteria are used to produce the customer's quality expectations
B. Acceptance criteria are less specific and precise than customer's quality expectations
C. Once agreed, acceptance criteria CANNOT be changed
D. Acceptance criteria should be agreed between the customer and the supplier
Answer: D
Q7. - (Topic 1)
Which is the purpose of the Change theme?
A. Prevent change to baselined products
B. Identify, assess and control any potential and approved changes to baselined products
C. Establish mechanisms to monitor and compare actual achievements against those planned
D. Assess and control uncertainty
Answer: B
Q8. - (Topic 2)
Which is a task of product-based planning?
A. Identify activities and dependencies
B. Write the Project Product Description
C. Prepare the Work Packages
D. Produce Product Status Accounts
Answer: B
Q9. - (Topic 1)
Why is the Initiating a Project process used?
A. To decide which project approach is suitable for the project
B. To fully understand how the project objectives will be achieved before committing significant resources
C. To produce the required Work Packages
D. To enable corporate or programme management to give authorization to deliver a project
Answer: B
Q10. - (Topic 2)
Which describes a risk event?
A. The area of uncertainty in terms of the threat or opportunity
B. The derivation or sources of a potential risk to the project
C. The achievement of a milestone on the Project Plan
D. The sequence of events and actions that will be put in place if a risk occurs
Answer: A