Q1. - (Topic 2)
Which role is responsible for creating Checkpoint Reports?
A. Senior Supplier
B. Team Manager
C. Change Authority
D. Project Support
Answer: B
Q2. - (Topic 2)
Which is a recommended quality review team role?
A. Project Manager
B. Assurance
C. Project Support
D. Administrator
Answer: D
Q3. - (Topic 2)
Identify the missing word(s) in the following sentence. During a quality review meeting [ ? ] any identified defects.
A. a solution should be designed for
B. an issue should be created for
C. the agreed actions should be recorded for
D. the chair will approve the solution to
Answer: C
Q4. - (Topic 1)
Which does NOT reflect the PRINCE2 principle of continued business justification?
A. There must be a justifiable reason for starting a project
B. The business justification drives decision making
C. If a project is no longer forecast to deliver a financial benefit, it should be stopped.
D. If a project can no longer be justified, it should be stopped
Answer: C
Q5. - (Topic 2)
Which is a purpose of a Project Brief?
A. Enable the assembly of the project mandate
B. Describe the reporting requirements of the various layers of management involved with the project
C. Describe how changes to products will be controlled
D. Provide a solid basis for the initiation of the project
Answer: D
Q6. - (Topic 1)
Which is NOT a purpose of a Benefits Review Plan?
A. Define the period over which the cost-benefit analysis will be based
B. Describe how to measure the performance of the project's products in operational use
C. Define the scope, timing and ownership of the benefit reviews required
D. Describe how to measure and confirm any benefits that are to be realised after the project is closed
Answer: A
Q7. - (Topic 1)
Which is a purpose of the Directing a Project process?
A. Provide the information required to confirm if it is worthwhile to initiate a project
B. Enable overall control of a project to be exercised by the Project Board
C. Establish the level of control required by the Project Board after initiation.
D. Provide sufficient information so that the current stage can be reviewed and the next Stage Plan approved
Answer: B
Q8. - (Topic 1)
Which is a purpose of the Controlling a Stage process?
A. Assign work to be done and take corrective action to ensure that the stage remains within tolerance
B. Provide a fixed reference point at which acceptance for the project product is confirmed
C. Enable the Project Board to be provided with sufficient information to authorize the next stage
D. Enable the organization to understand the work that needs to be done to deliver the project's products
Answer: A
Q9. - (Topic 1)
Identify the missing words in the following sentence. At the end of a stage, the [ ? ] should be used to check whether there is a requirement to send copies of the End Stage Report to external interested parties.
A. Stage Plan
B. Communication Management Strategy
C. Follow-on action recommendations
D. Quality Management Strategy
Answer: B
Q10. - (Topic 2)
Which is one of the three levels of plan in PRINCE2?
A. Benefits Review Plan
B. Programme Plan
C. Team Plan
D. Project Brief
Answer: C