Q1. - (Topic 1)
Which statement about the Directing a Project process is true?
A. Provides a mechanism for the Project Board to assure that there is continued business justification
B. Covers the day-to-day activities of the Project Manager
C. Ensures there are regular progress meetings
D. Begins on completion of the Initiating a Project process
Answer: A
Q2. - (Topic 2)
What product would enable the Project Manager to review how a Work Package is performing against its cost tolerance?
A. Configuration Item Record
B. Quality Register
C. Highlight Report
D. Checkpoint Report
Answer: D
Q3. - (Topic 2)
Which of the following statements about lines of authority and reporting are true?
1.
The Project Manager has day-to-day control for a management stage within the limits laid down by the Project Board.
2.
If a Team Manager forecasts a deviation beyond Work Package tolerances, this should be referred to the Project Manager.
A. Only 1 is true
B. Only 2 is true
C. Both 1 and 2 are true
D. Neither 1 or 2 are true
Answer: C
Q4. - (Topic 1)
Which is an objective of the Closing a Project process?
A. Prepare the plan for the next stage
B. Assess any benefits that have already been realized
C. Produce a Benefits Review Plan to identify what benefits are expected
D. Check that all benefits are realized before closing a project
Answer: B
Q5. - (Topic 2)
Which is a purpose of a Lessons Log?
A. Note any lessons that are raised in Checkpoint Reports
B. Record that corrective action is being taken
C. Escalate lessons to the Project Board
D. Raise improvements with Project Assurance
Answer: A
Q6. - (Topic 1)
A product can NOT be supplied to meet all of the requirements in its baselined Product Description. What first action should be taken?
A. Raise a request for change
B. Raise an off-specification
C. Write an Exception Report
D. Amend the Work Package
Answer: B
Q7. - (Topic 2)
What product defines the reporting requirements between the Project Manager and Team Manager?
A. Project Brief
B. Product Description
C. Team Plan
D. Work Package
Answer: D
Q8. - (Topic 2)
Which statement applies to Stage Plans?
A. Always have the same duration as the Project Plan
B. Are produced at the same time as the Project Initiation Documentation
C. Assist the Project Manager in the day-to-day running and control of the project
D. Provide a baseline against which the Project Board monitor overall progress
Answer: C
Q9. - (Topic 1)
Which is NOT a purpose of the Initiating a Project process?
A. Enable a Project Board decision about the commitment of resources to a project
B. Enable an organization to understand the work that needs to be done to deliver a project's products before a project is approved
C. Establish solid foundations for a project
D. Enable the Project Board to decide whether it is worthwhile to initiate a project
Answer: D
Q10. - (Topic 2)
Which is a FALSE statement about technical stages?
A. Can overlap with other technical stages
B. Typified by the use a particular set of specialist skills
C. Include the Managing a Stage Boundary process activities
D. Can span more than one management stage
Answer: C