NEW QUESTION 1
Who is accountable for tracking the remaining work toward the Sprint Goal? (Choose the best answer.)

  • A. The Developers.
  • B. The Scrum Master.
  • C. The Product Owner.
  • D. The Project Manager.

Answer: A

NEW QUESTION 2
The IT manager asks a Development Team for a status report describing the progress throughout the Sprint. The Development Team asks the Scrum Master for advice. The Scrum Master should:
(Choose the best answer.)

  • A. Talk to the IT manager and explain that progress in Scrum comes from inspecting an Increment at the Sprint Review.
  • B. Tell the Development Team to figure it out themselves.
  • C. Tell the Development Team to fit the report into the Sprint Backlog.
  • D. Create and deliver the report to the manager herself.
  • E. Ask the Product Owner to send the manager the report.

Answer: A

NEW QUESTION 3
For which is the Scrum Master responsible?

  • A. Managing the performance of the Scrum Team.
  • B. The meetings and the objectives that a Scrum Team sets for itself.
  • C. The Scrum framework being adopted and used properly.
  • D. Keeping track of resource allocation.

Answer: C

NEW QUESTION 4
What are the two primary ways a Scrum Master keeps a Development Team working at its highest level of productivity? (Choose two.)

  • A. By ensuring the meetings start and end at the proper time.
  • B. By removing impediments that hinder the Development Team.
  • C. By facilitating Development Team decisions.
  • D. By keeping high value features high in the Product Backlog.

Answer: BC

NEW QUESTION 5
Every Development Team should have:

  • A. At least one representative from each major software engineering discipline (like QA, Dev, UX).
  • B. The competencies and skills needed to deliver a Done Increment in a Sprint.
  • C. One Lead Developer and no more than 8 other members.

Answer: B

NEW QUESTION 6
When must a Product Owner release each Increment? (Choose the best answer.)

  • A. When it makes sense.
  • B. When the Scrum Team finishes their work.
  • C. Whenever the product is free of defects.
  • D. After every Sprint, Without exception.

Answer: A

NEW QUESTION 7
What is the recommended size for a Scrum Team? (Choose the best answer.)

  • A. At least 7.
  • B. 9
  • C. 10 or fewer.
  • D. 7 plus or minus 3.

Answer: C

NEW QUESTION 8
What does it mean to say that an event has a time-box?

  • A. The event must happen at a set time.
  • B. The event must happen by a given time.
  • C. The event must take at least a minimum amount of time.
  • D. The event can take no more than a maximum amount of time.

Answer: D

NEW QUESTION 9
The Sprint Review is mainly an inspect and adapt opportunity for which group?

  • A. The Development Team and stakeholders.
  • B. The Product Owner and Development Team.
  • C. The Scrum Team and stakeholders.
  • D. The Product Owner and management.
  • E. The Development Team and management.
  • F. The Product Owner and stakeholders.

Answer: C

NEW QUESTION 10
As the Development Team starts work during the Sprint, it realizes it has selected too much work to finish in the Sprint. What should it do?

  • A. Inform the Product Owner at the Sprint Review, but prior to the demonstration.
  • B. Find another Scrum Team to give the excess work to.
  • C. As soon as possible in the Sprint, work with the Product Owner to remove some work or Product Backlog items.
  • D. Reduce the definition of “Done” and get all of the Product Backlog items “Done” by the new definition.

Answer: C

NEW QUESTION 11
Which three of the following are time-boxed events in Scrum? (Choose three.)

  • A. Release Testing.
  • B. Release Retrospective.
  • C. Sprint Retrospective.
  • D. Sprint Planning.
  • E. Sprint Testing.
  • F. Sprint 0.
  • G. Daily Scrum.

Answer: CDG

NEW QUESTION 12
Sprint burndown charts are an efficient tracking tool, because they show:

  • A. An estimate of the total work remaining for the Sprint.
  • B. How much effort has gone into a Sprint.
  • C. How many hours have been worked by each Development Team member.
  • D. How many Product Backlog items remain.

Answer: A

NEW QUESTION 13
Scrum has a role called “Project Manager”.

  • A. True
  • B. False

Answer: B

NEW QUESTION 14
Which answer best describes the topics covered in Sprint Planning?

  • A. What to do and who will do it.
  • B. How conditions have changed and how the Product Backlog should evolve.
  • C. What can be done and how to do it.
  • D. What went wrong in the last Sprint and what to do differently this Sprint.
  • E. Who is on the team and what team member roles will be.

Answer: C

NEW QUESTION 15
A Scrum Team is a cohesive unit of professionals that consists of which of the following? (Choose all that apply.)

  • A. Users.
  • B. One Scrum Master.
  • C. Developers.
  • D. Customers.
  • E. One Product Owner.

Answer: BCE